Category: RERA

  • Karnataka HC Sends Developer to RERA Appellate Tribunal Over Refund Dispute

    Karnataka HC Sends Developer to RERA Appellate Tribunal Over Refund Dispute

    Date: 04.11.2026

    The Karnataka High Court has dismissed a developer’s writ petition challenging a RERA refund order, holding that the dispute must be pursued through the statutory appellate remedy available under the Real Estate (Regulation and Development) Act, 2016.

    Background of the dispute

    The case arose from an agreement dated 14 June 2012 for the purchase of residential Site No. C68 in the M/s Asset Habitat project in Mysore. The agreed sale price was Rs.21.60 lakh.

    According to the record, the purchaser and her husband initially paid Rs.7 lakh, which was acknowledged by the developer. They later paid further amounts, bringing the amount claimed before the Karnataka Real Estate Regulatory Authority (KRERA) to Rs.12.40 lakh.

    The purchaser alleged that the project was not completed and that the site had not been conveyed even by 2018. After repeated reminders did not resolve the issue, she filed a complaint before KRERA in 2020 seeking a refund, interest and compensation.

    RERA proceedings and refund direction

    KRERA initially passed an order on 22 May 2020 after the developer did not participate in the proceedings. It directed refund of Rs.12.40 lakh, with interest at 9% per annum up to 30 April 2017 and thereafter at 2% above the State Bank of India’s MCLR until payment.

    The developer subsequently sought to set aside that order, contending that notice had not been properly served. KRERA allowed that application on 15 December 2020 and restored the complaint for fresh consideration.

    The matter was then heard over multiple dates between 2021 and 2023. The developer was allowed to place final written submissions on record. KRERA ultimately passed its fresh order on 24 August 2023, which became the subject of the High Court challenge.

    Why the High Court declined to examine the merits

    The developer approached the High Court under Articles 226 and 227 of the Constitution, arguing that the RERA order violated principles of natural justice and that the appellate tribunal was not functioning when the writ petition was filed.

    The Court rejected both grounds:

    • Functional appellate remedy: The Court noted that the RERA Appellate Tribunal has since been constituted and is functioning. The earlier difficulty concerning the tribunal’s availability therefore no longer existed.
    • Adequate opportunity to be heard: The Court found that the developer had received sufficient opportunity after the earlier ex parte order was recalled. The proceedings remained pending for a substantial period, hearings were held, and the developer filed additional objections and written submissions before the matter was decided.
    • RERA jurisdiction upheld: The Court held that KRERA had jurisdiction to decide the purchaser’s complaint because it concerned alleged non-compliance with the sale agreement.

    The Court reiterated that a writ petition is ordinarily not entertained when a statutory appeal is available, unless there is a fundamental-rights issue, a genuine breach of natural justice, a complete lack of jurisdiction, or a challenge to the validity of legislation. It found that none of these exceptions applied.

    Court’s decision

    Justice T.P. Vivekananda dismissed the writ petition as not maintainable. Importantly, the dismissal was not a ruling on the underlying merits of the refund dispute.

    The Court preserved the developer’s right to file a statutory appeal under Section 43(5) of the RERA Act. It also clarified that the developer may seek exclusion, under Section 14 of the Limitation Act, of the time spent pursuing the matter before the High Court from 2 January 2024.

    All factual and legal contentions of both sides have been left open for consideration by the appellate authority, which has been directed to assess any appeal independently and without being influenced by the High Court’s observations.

    Key legal takeaway

    The ruling reinforces that parties challenging RERA orders should generally use the appeal mechanism provided by the RERA Act. A writ petition cannot ordinarily replace that remedy merely because a party disputes the decision on merits; a demonstrable jurisdictional defect or real denial of a fair hearing is required before the High Court will intervene directly.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Punjab and Haryana High Court Rejects Repeated RERA Claims

    Punjab and Haryana High Court Rejects Repeated RERA Claims

    Date: 03.11.2026

    The Punjab and Haryana High Court has dismissed a homebuyers’ appeal against Tata Housing Development Company Ltd., holding that repeated complaints arising from the same apartment dispute could not be pursued in successive proceedings.

    Case at a glance

    In Ashok Kumar Soni and others v. M/s Tata Housing Development Company Limited, decided on 2 September 2026, the High Court upheld the Haryana Real Estate Appellate Tribunal’s decision to reject the appellants’ challenge. The case concerned an apartment in Tata Housing’s Premanti project in Sector 72, Gurugram.

    The apartment had been allotted to the appellants for β‚Ή2,77,74,702, under an Apartment Buyer’s Agreement dated 16 August 2014. Possession was offered on 28 June 2017.

    Homebuyers’ allegations

    The buyers had raised several grievances concerning the apartment and the project. They alleged that the developer had overcharged them after learning that 10 apartments of the same size had reportedly been sold to Oriental Bank of Commerce for β‚Ή2.18 crore each. They initially sought a refund of β‚Ή66 lakh.

    Their complaints also referred to delayed possession, deficiencies in promised facilities, alleged changes to the project’s site plan, and a claimed change in the main entrance of Tower II. They sought compensation for financial loss, mental agony, and physical loss.

    History of repeated proceedings

    The dispute had already gone through several rounds before the Haryana RERA Authority, the Adjudicating Officer, and the Appellate Tribunal:

    • The first complaint resulted in possession and delayed-possession charges being granted.
    • An appeal against that order was withdrawn, while reserving the buyers’ right to seek compensation for alleged non-availability of facilities.
    • A later compensation complaint was dismissed by the Adjudicating Officer on 15 September 2021.
    • The buyers’ appeal from that decision was also withdrawn on 31 March 2023, without liberty to file another case.
    • A second compensation complaint was then filed, alleging material changes in the site plan and deficiencies in facilities. It was dismissed on 13 January 2025.

    The Adjudicating Officer found that the buyers had not produced evidence supporting the alleged site-plan changes or road-access issues. Neither the purported original or revised site plan nor other proof of the asserted changes was placed on record.

    Why the appeal failed

    The High Court concluded that the buyers had been aware of their grievances when they initiated the earlier proceedings but had nonetheless pursued sequential complaints regarding the same apartment and substantially connected claims.

    The Court held that such repeated litigation was barred by the principles of res judicata and Order II Rule 2 of the Code of Civil Procedure, 1908. These principles prevent parties from re-litigating matters that have already been decided, or from splitting claims arising from the same cause of action across multiple cases.

    The Court also examined Sections 88 and 89 of the Real Estate (Regulation and Development) Act, 2016. While RERA has overriding effect in case of conflict, Section 88 preserves the operation of other laws where they do not conflict with the Act. The Court therefore found that relevant procedural principles of the CPC could apply to RERA proceedings.

    Court’s key observation

    The Court stressed that permitting multiple complaints based on known, connected grievances would be contrary to public policy. It found no factual or legal defect in the Appellate Tribunal’s order and dismissed the appeal as lacking merit.

    Significance for RERA disputes

    The ruling reinforces that homebuyers and developers should present all known claims relating to a transaction in the appropriate proceeding, supported by documentary evidence. A party cannot ordinarily revive or divide claims through successive complaints after earlier proceedings have been decided or withdrawn without permission to refile.

    For site-plan or amenity-related claims in particular, the case highlights the importance of filing concrete evidence, such as sanctioned plans, revised plans, contractual representations, correspondence, photographs, and other records demonstrating the alleged deviation.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Delhi High Court Ruled Deemed Occupancy Certificate Claim Cannot Override RERA

    Delhi High Court Ruled Deemed Occupancy Certificate Claim Cannot Override RERA

    Date: 02.11.2026

    The Delhi High Court has dismissed two appeals by CJ Infrastructure Pvt. Ltd., holding that the developer could not avoid the Real Estate (Regulation and Development) Act, 2016 (RERA) on the basis of a claimed β€œdeemed” occupancy certificate and was required to comply with the statutory pre-deposit condition before its appeals could be heard.

    Background: Metroplex East commercial complex

    CJ Infrastructure developed Metroplex East, a commercial complex at 21, District Centre, Laxmi Nagar, Delhi. The project comprises 197 units along with common areas, including the entrance lobby, elevators and staircases. The developer stated that construction was completed on 14 February 2013 and that an architect had certified the building as fit for occupation.

    According to the company, it applied to the Delhi Development Authority (DDA) for an Occupancy-cum-Completion Certificate (OCC) in 2013 and early 2014. It argued that, because the DDA did not respond within the applicable period, the OCC should be treated as having been granted by operation of the building bye-laws.

    Between 2013 and 2015, the company sold or allotted 149 commercial units and executed registered conveyance deeds in favour of purchasers. Later, several purchasers initiated proceedings under RERA, principally alleging that the developer had not obtained a formal OCC for the building.

    The central dispute: Was the OCC deemed to have been granted?

    The developer’s principal argument was that the project had effectively been completed before RERA came into force and that a deemed OCC had arisen because of the DDA’s alleged inaction. On that basis, it contended that the RERA authorities lacked jurisdiction over the complaints.

    The Court did not accept this position. It examined the record placed by the DDA and highlighted key deficiencies:

    • The developer claimed that it had applied for completion on 14 February 2013, but the Fire Safety Certificate relied upon was dated 30 October 2013. The certificate was required for a completion application.
    • The OCC-fee receipt produced by the developer was dated 20 April 2017, approximately four years after the claimed OCC application.
    • The DDA reported deviations from the sanctioned plan.
    • The application was scrutinised under the Unified Building Bye-Laws, 2016, and the stated deficiencies were not rectified despite opportunities to do so.
    • The DDA rejected the OCC application on 8 September 2021.

    The Court held that a deemed OCC could not be claimed in these circumstances. It noted that deemed approval requires the applicant to have met the necessary requirements, including payment of applicable fees, and cannot authorise conduct contrary to lease conditions, the master plan, regulations or building bye-laws.

    Most importantly, the Court found that no OCC existed when the appeals were before the Real Estate Appellate Tribunal (REAT). Therefore, the project remained subject to RERA.

    Why the RERA pre-deposit requirement applied

    The second major issue concerned Section 43(5) of RERA. This provision requires a promoter challenging an order before the appellate tribunal to first deposit at least 30% of the penalty, or such higher percentage as the tribunal directs, or the total amount payable to the allottee, including interest and compensation, depending on the nature of the order.

    The REAT had required CJ Infrastructure to deposit the full adjudicated amounts as a condition for continuing its appeals. When the company did not make that deposit, the REAT dismissed the appeals.

    The Delhi High Court upheld that decision. It emphasised that the statutory wording, including β€œit shall not be entertained,” makes pre-deposit a mandatory threshold condition for a promoter’s appeal. The Court relied on the Supreme Court’s ruling in Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh, which had held that this requirement is not unconstitutionally burdensome and serves to protect allottees’ financial interests.

    The Court also rejected the developer’s offer to provide immovable-property security instead of making the deposit. RERA contains no provision permitting such a substitute.

    Judgment and implications

    The High Court found no error in the REAT’s orders and dismissed both appeals. It nevertheless allowed the appellants an opportunity to seek revival of their REAT appeals within 30 days of the judgment, provided they comply with the applicable pre-deposit condition under Section 43(5).

    The ruling reinforces two important principles for real-estate developers:

    1. A deemed occupancy certificate cannot be assumed merely from alleged administrative inaction. The applicant must show compliance with the applicable approval requirements, including supporting documentation, fees and rectification of identified shortcomings.
    2. The RERA pre-deposit requirement is mandatory for promoters’ appeals. A developer cannot ordinarily have an appeal heard by REAT without first making the required statutory deposit, and offering property as security is not an authorised alternative.

    The judgment, pronounced on 29 August 2025 by a Division Bench of Justice Anil Kshetarpal and Justice Harish Vaidyanathan Shankar, underscores the courts’ approach of enforcing RERA’s safeguards for allottees while requiring strict compliance from promoters seeking appellate relief.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Bombay High Court Upholds Maha RERA Appellate Tribunal’s Power to Restore Defaulted Proceedings

    Bombay High Court Upholds Maha RERA Appellate Tribunal’s Power to Restore Defaulted Proceedings

    Date: 26.10.2026

    The Bombay High Court has held that the Maharashtra Real Estate Appellate Tribunal may restore proceedings dismissed for non-prosecution when sufficient cause is shown, even though RERA does not expressly state that power.

    Background of the dispute

    Hubtown Ltd. challenged an order of the Maharashtra Real Estate Appellate Tribunal that revived an allottee’s delayed appeal. The allottee had originally filed a complaint under Section 18 of the Real Estate (Regulation and Development) Act, 2016, seeking relief from Maha RERA. Maha RERA dismissed that complaint on 23 April 2024.

    The allottee then appealed to the Appellate Tribunal, accompanied by an application seeking condonation of a 25-day filing delay. On 3 July 2025, the application was dismissed for want of prosecution because the allottee did not appear. As a consequence, the appeal was also disposed of.

    The allottee subsequently sought restoration of both the delay-condonation application and the appeal, along with condonation of the delay in making the restoration request. The Appellate Tribunal allowed those applications, relying in part on its inherent powers under Regulation 25 of the Maharashtra Real Estate Appellate Tribunal Regulations, 2019.

    The promoter’s challenge

    Hubtown argued that the Appellate Tribunal, as a statutory body, could exercise only those Civil Court powers expressly specified in Section 53(4) of RERA. While that provision permits dismissal for default or ex parte proceedings, it does not specifically confer a power to restore a matter dismissed in default.

    The promoter also contended that Regulation 25 could not enlarge the Tribunal’s jurisdiction beyond RERA and its rules, and that the allottee had not shown adequate cause for delay.

    High Court’s reasoning

    Justice N. J. Jamadar rejected the narrow reading of Section 53. The Court emphasized three connected principles:

    • Natural justice governs the Tribunal’s procedure. Section 53(1) states that the Appellate Tribunal is not bound by the strict procedure of the Code of Civil Procedure and must be guided by natural justice.
    • The Tribunal can regulate its own procedure. Section 53(2) authorizes it to do so, subject to RERA.
    • Necessary incidental powers are implied. A tribunal must possess powers that are ancillary and essential to perform its statutory functions effectively, unless the statute expressly prohibits their use.

    The Court found that the power to restore a case dismissed for default is a natural counterpart to the power to dismiss it for non-appearance. A tribunal may dismiss a matter when a party does not appear, but fairness may require it to restore the matter if the party later establishes good cause for the absence.

    Supreme Court precedents relied upon

    The judgment drew support from established Supreme Court decisions:

    • In New India Assurance Co. Ltd. v. R. Srinivasan, the Supreme Court recognized that a judicial or quasi-judicial body which may dismiss a proceeding for non-prosecution also has inherent jurisdiction to restore it upon a showing of good cause.
    • In Union of India v. Paras Laminates (P) Ltd., the Court held that statutory tribunals have powers expressly granted as well as powers necessarily incidental to making their jurisdiction effective.
    • In Grindlays Bank Ltd. v. Central Government Industrial Tribunal, the Supreme Court held that a tribunal may set aside an ex parte award in the interests of justice even without an express provision, absent any statutory prohibition.

    Applying these principles, the Bombay High Court held that the Appellate Tribunal’s restoration power exists independently of Regulation 25 because it is essential to achieving RERA’s purpose and to deciding matters fairly.

    Limited scope for interference with delay condonation

    The Court also declined to interfere with the Tribunal’s decision to condone delay. It observed that once the first adjudicatory forum has exercised positive discretion to condone delay after assessing the explanation and supporting documents, an appellate or supervisory court should not lightly overturn that decision.

    Interference would generally be justified only where the order is perverse or where delay has been condoned without any reasons. The Court found neither circumstance present and held that no substantial question of law arose.

    Outcome and legal significance

    The Bombay High Court dismissed Hubtown’s second appeal and disposed of the related interim application. The ruling confirms that the Maha RERA Appellate Tribunal is not confined to a mechanical reading of its expressly listed powers. Consistent with natural justice, it may restore a proceeding dismissed in default where sufficient cause is established and no statutory prohibition applies.

    This ensures that procedural lapses do not automatically defeat a party’s substantive right to have a real-estate dispute adjudicated on its merits.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Punjab & Haryana HC Denies Anticipatory Bail in LLP Partnership Dispute Involving Alleged Forgery

    Punjab & Haryana HC Denies Anticipatory Bail in LLP Partnership Dispute Involving Alleged Forgery

    Date: 24.10.2026

    The Punjab and Haryana High Court has declined anticipatory bail to two partners of M/s GLK Homes LLP in a case involving allegations of forged retirement documents, unpaid settlement amounts, and an alleged attempt to remove a partner from the business.

    Background of the dispute

    The case arose from a dispute within M/s GLK Homes LLP, a firm incorporated in June 2020. The complainant, Devender Singh, alleged that he had joined the firm as a partner and contributed to its business and management. According to the complaint, disagreements later developed between the partners, after which the accused allegedly conspired to exclude him from the firm and deny him his share in its capital, profits, and goodwill.

    The complainant alleged that the accused had offered to dissolve the business arrangement by paying him β‚Ή13.50 crore. While β‚Ή50 lakh was transferred through RTGS, he claimed that the remaining amount was not paid. Three cheques dated 1 April 2022 were allegedly issued for the balance, but the account from which they were drawn had been closed.

    He further alleged that a retirement deed was fabricated to show that he had voluntarily retired from the LLP after receiving a full and final settlement. The allegedly forged document was submitted to the Registrar of Companies to create a record that he had left the firm.

    Petitioners’ defence

    The petitioners argued that the matter was essentially a delayed commercial dispute concerning land transactions and partnership arrangements. They maintained that β‚Ή50 lakh had been paid to the complainant because it represented his agreed capital contribution to the LLP, not a settlement of β‚Ή13.50 crore.

    Their case was that the alleged larger payment arrangement was oral, undocumented, and implausible. They also contended that the complainant had resigned voluntarily in September 2020 and that his entitlement to payment depended on conditions relating to acquisition of land and regulatory approvals.

    The petitioners relied on a video recording which they claimed showed voluntary execution of the relevant documents. They also stressed that they had cooperated with the investigation and that the disputed original documents were already in the investigating agency’s possession.

    Land transaction context

    The dispute was connected with approximately 11.26 acres of land in Village Sihi, Faridabad. The petitioners described a sequence of earlier agreements involving landowners, M/s Bonanza Promoters Pvt. Ltd., M/s Crown Township Pvt. Ltd., and entities associated with the complainant.

    According to their submissions, M/s GLK Homes LLP acquired the land in July 2020 through registered transactions worth more than β‚Ή47 crore. The petitioners claimed that they had arranged substantial funds for the transaction after the complainant and another associate were unable to finance the project.

    They also referred to a separate dispute involving M/s Shail Developers Ltd., which had advanced β‚Ή2.50 crore. That amount was later returned by M/s GLK Homes LLP under a compromise arrangement.

    Forensic findings weighed heavily with the Court

    The State and the complainant opposed anticipatory bail, relying on findings of the Regional Forensic Science Laboratory, Bhondsi. The forensic examination reportedly found the compromise deed, retirement deed, and board-meeting minutes to be forged.

    Most significantly, the Court noted that the complainant’s signatures on the disputed retirement documents were found to have been lifted from another document. The Court also found that the petitioners’ video-recording claim did not displace the forensic material at the bail stage.

    The Court observed that it appeared doubtful that the complainant would have resigned shortly after sale deeds were executed in the LLP’s favour in July 2020 merely in exchange for β‚Ή50 lakh, particularly given the scale of the underlying land transaction and the complainant’s asserted financial involvement.

    Court’s decision

    Justice Shalini Singh Nagpal held that anticipatory bail is an extraordinary form of protection and cannot be claimed as a matter of right. While the Court acknowledged that custodial interrogation might not be necessary solely because the petitioners had previously joined the investigation, it held that this was not enough to justify pre-arrest bail.

    The seriousness of the alleged forgery, the forensic findings, and the petitioners’ attributed role were treated as decisive factors. The Court concluded that no strong or exceptional circumstances had been shown to warrant anticipatory bail.

    The petition was therefore dismissed.

    Key legal takeaway

    The decision illustrates that in allegations of business-partnership fraud, the existence of documentary evidence does not automatically favour anticipatory bail. Where forensic material indicates that signatures or corporate records may have been fabricated, courts may treat the allegations as serious enough to deny pre-arrest protection even if the dispute also has commercial and civil dimensions.

    Listen to this on our #YouTube Channel

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Bombay HC: RERA Appellate Tribunal Cannot Decide Merits of Complaint Rejected on Maintainability β€” Mandatory Remand to MahaRERA

    Bombay HC: RERA Appellate Tribunal Cannot Decide Merits of Complaint Rejected on Maintainability β€” Mandatory Remand to MahaRERA

    Date: 23.10.2026

    The Bombay High Court has held that where MahaRERA dismisses a complaint solely on maintainability, the Maharashtra Real Estate Appellate Tribunal must remand the matter for a merits decision if it reverses that finding; it cannot decide the dispute itself for the first time.

    Key ruling

    In Keyana Estate LLP v. Ashok D. Karwa and Another, decided on 21 October 2026, the Court set aside a MahaRERA Appellate Tribunal order that proposed to decide allottees’ complaint on merits after finding it maintainable despite an arbitration clause.

    The Court ruled that MahaRERA, as the original adjudicatory authority, must first determine the factual and legal merits of the complaint. The Tribunal’s role is appellate and corrective; it cannot replace the first-instance decision-making process where no merits determination has yet been made.

    Background of the dispute

    The allottees had filed a complaint before MahaRERA against Keyana Estate LLP. MahaRERA dismissed it at the threshold, holding that the agreement’s arbitration clause made the complaint not maintainable.

    The allottees appealed. The Appellate Tribunal disagreed with MahaRERA’s view on maintainability and held that the complaint could proceed notwithstanding the arbitration clause. However, rather than sending the matter back to MahaRERA, the Tribunal directed that it would decide the substantive merits itself.

    Keyana Estate LLP challenged that procedural course before the Bombay High Court.

    Why remand was necessary

    The High Court emphasized that an appeal is a statutory remedy and cannot be reduced by allowing an appellate forum to decide merits in the first instance. If the Tribunal were to determine the complaint’s merits without a prior MahaRERA decision, the affected party would lose a full appellate level on those merits and would be left to challenge the Tribunal’s first-instance findings only before the High Court.

    The Court described the proper sequence as follows:

    1. The original forum decides the complaint on merits.
    2. An appellate forum reviews that merits decision if challenged.
    3. A higher court may then consider a further appeal where legally available.

    When a case is dismissed only on a preliminary issue, and the appellate body overturns that preliminary ruling, the normal and appropriate course is to return the matter to the original forum for adjudication.

    Distinguishing routine-remand cases

    The respondents relied on the Supreme Court’s ruling in Nadakerappa v. Pillamma, which cautions that remand should not be ordered routinely where the lower court has already decided the matter on merits and the appellate court has the complete evidentiary record.

    The Bombay High Court distinguished that principle. It explained that the Supreme Court’s caution applies where a merits decision already exists. It does not apply where the original authority never considered the merits at all because it dismissed the matter on a preliminary ground.

    In this situation, remand is not an unnecessary procedural exercise. It protects the parties’ right to an adjudication at the first level and preserves the ordinary appellate structure.

    Court’s directions

    The High Court allowed the second appeal and:

    • set aside the Appellate Tribunal’s order dated 19 March 2025;
    • remanded Complaint No. CC0600000094344 to MahaRERA for a decision on merits;
    • directed MahaRERA to decide the complaint as expeditiously as possible, preferably within six weeks, noting that the complainants are senior citizens; and
    • kept all parties’ substantive contentions open.

    Practical significance for real-estate disputes

    The ruling reinforces an important procedural safeguard in MahaRERA litigation. An arbitration clause may be assessed at the maintainability stage, but if MahaRERA’s threshold dismissal is overturned, the merits ordinarily must go back to MahaRERA rather than being determined for the first time by the Appellate Tribunal.

    For promoters, allottees and practitioners, the decision confirms that procedural efficiency cannot override the statutory right to a first-instance merits ruling and a meaningful appeal from that ruling.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Bombay High Court: Deemed Conveyance Orders Cannot Ignore Builder’s FSI and Development Rights Objections β€” Section 11 MOFA Order Set Aside

    Bombay High Court: Deemed Conveyance Orders Cannot Ignore Builder’s FSI and Development Rights Objections β€” Section 11 MOFA Order Set Aside

    Date: 21.10.2026

    The Bombay High Court has set aside a deemed conveyance order granted to a housing society in Vile Parle, holding that the competent authority failed to deal with material objections and provide adequate reasons for its decision.

    Background of the dispute

    The case concerns a 4,133.68 sq. metre plot at Dixit Road, Vile Parle (East), Mumbai, comprising Plot Nos. 157, 158 and 159 and Final Plot No. 324 of TPS II. M/s. Vimal Builders, now the proprietorship of petitioner Hasmukh Narrotamdas Malkan, had agreed to purchase the land in 1973. A residential building, Vimal Apartments, was constructed and completed in 1975, and flats were sold to individual purchasers.

    The flat purchasers formed the Vile Parle Vimal Gauri Co-operative Housing Society Ltd. in 1982. The builder later obtained conveyance of the land pursuant to a decree for specific performance against the original owners.

    The society sought conveyance of the property, first through a civil suit and later through an application for deemed conveyance under Section 11 of the Maharashtra Ownership Flats Act, 1963 (MOFA). In March 2025, the District Deputy Registrar granted deemed conveyance of the entire plot to the society.

    Why the builder challenged the order

    The petitioner contended that the authority had not properly considered key issues affecting the extent of the society’s entitlement. These included:

    • The agreements for sale, which the petitioner said contemplated development of more than one building on the land.
    • The petitioner’s asserted right to use remaining development potential, including FSI/TDR, for a second building.
    • A 1976 sanctioned layout plan and the claimed existence of a plinth for the proposed second building.
    • Alleged statements in the society’s earlier civil plaint that recognised the petitioner’s right to use the balance FSI.
    • The authority of the society’s secretary to institute the deemed conveyance application.

    The builder argued that a summary proceeding under MOFA does not remove the authority’s duty to consider relevant documents and explain why significant objections are rejected.

    Court’s findings

    Justice Farhan P. Dubash found that the competent authority had referred to the promoter’s statutory obligation to convey property and to clause 22 of the flat-purchase agreements. However, it did not address other contractual clauses and documents relied on by the petitioner.

    The Court held that simply recording a party’s submissions is not enough. A quasi-judicial authority must show that it has considered the material disputes relevant to the relief sought and must give reasons for its conclusions.

    The judgment identified three central deficiencies in the 2025 order:

    • Contractual documents were not fully examined: The authority did not explain why the agreements and clauses said to support a multi-building layout did not affect the society’s claim to the entire plot.
    • FSI and second-building objections were not addressed: The authority did not assess the relevance of the alleged admission in the society’s earlier plaint, the 1976 plan, or the claimed surviving plinth.
    • Secretary’s authority was left undecided: The order contained no finding on the objection that the society’s secretary lacked authority to file the application.

    The Court stressed that the issue was not that the authority’s reasons were too brief. Rather, the order lacked reasoned consideration of material points that could directly affect the scope of conveyance.

    Importance of the earlier remand

    The application had already been remanded once by the High Court in November 2024, with a specific direction to consider the parties’ submissions and issue reasoned findings. The Court held that the authority’s failure to address the material objections also amounted to non-compliance with that direction.

    The Court further noted that the authority had initially rejected the society’s application in 2023 on the basis that ownership disputes could not be decided in summary proceedings. After remand, it reached the opposite result on the same broad factual record without adequately explaining why the society was entitled to the conveyance sought.

    The ruling and its implications

    The High Court set aside the deemed conveyance order dated 20 March 2025 and remitted the society’s 2021 application to the District Deputy Registrar for fresh consideration.

    The authority must now hear all parties, consider their material submissions and relevant documents, and issue a reasoned order by 31 March 2027. The Court did not decide whether the society is ultimately entitled to deemed conveyance, whether the entire plot should be conveyed, or whether the builder’s claims regarding FSI and a second building are valid.

    The decision reinforces an important principle in MOFA deemed conveyance proceedings: although the jurisdiction is summary, authorities must still assess the relevant agreements and evidence, address material objections, and clearly explain the basis of their decision. The outcome on the merits remains open for determination by the competent authority.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Delhi HC: Homebuyers Cannot Bypass RERA Proceedings by Filing Fresh Civil Suits Against Builders

    Delhi HC: Homebuyers Cannot Bypass RERA Proceedings by Filing Fresh Civil Suits Against Builders

    Date: 19.10.2026

    The Delhi High Court has dismissed Lalit Kumar’s appeal against the rejection of a wide-ranging civil suit brought by 12 homebuyers against E-Homes Infrastructure Pvt. Ltd., holding that the claims were vague, time-barred in part, barred by prior proceedings in part, and improperly combined multiple independent disputes.

    Background of the dispute

    The case arose from allegations by purchasers of apartments in The Jewel of Noida, a group-housing project developed by E-Homes Infrastructure Pvt. Ltd. The homebuyers alleged shortcomings in the project’s development, maintenance arrangements, owners’ association, electricity services, parking, charges, and contractual documentation.

    According to the plaintiffs, the developer had represented that the project would provide high-quality facilities and amenities. They later alleged a substantial mismatch between the apartments’ actual or carpet areas and the super areas on which charges were based. They also challenged several levies, including maintenance, club, electricity-meter, preferential-location, green-belt, lease-rent, tax, and parking charges.

    The plaintiffs further alleged that the developer had not transferred maintenance responsibilities to a lawful apartment owners’ association despite possession having been offered years earlier. They disputed the formation and functioning of the registered association, claiming that it was created through irregular procedures and without proper elections.

    Reliefs sought by the homebuyers

    The suit sought a broad set of remedies, including:

    • Restoration of essential services, including garbage collection and DG electricity supply;
    • Refunds for alleged excess area charges, maintenance charges, club charges, electricity-related charges, taxes, interest, parking charges, preferential-location charges, and green-belt charges;
    • Appointment of an independent architect, consultant, or court commissioner to measure carpet area, super area, and loading;
    • Directions concerning maintenance accounts and transfer of maintenance to an owners’ association;
    • Changes to allegedly one-sided provisions in the sub-lease deeds;
    • Adequate and independent parking arrangements; and
    • Compensation, punitive damages, and rendition of accounts.

    Why the civil suit was rejected

    The trial court dismissed the suit on 31 August 2024. On appeal, the High Court found no reason to interfere with that decision.

    1. Maintenance and electricity issues had already been pursued before RERA

    The court noted that disputes concerning electricity and maintenance charges were already before U.P. RERA and were subject to related proceedings. Under Section 79 of the RERA Act, civil courts cannot entertain matters that fall within the jurisdiction of the RERA authorities or appellate tribunal.

    The court therefore held that the plaintiffs could not use a civil suit to reopen or nullify adverse outcomes from the competent regulatory forum.

    2. Monetary recovery claims were beyond limitation

    The homebuyers’ refund claims were connected to purchases that had culminated in individual sale deeds. The suit was filed in 2024, while the relevant limitation period for recovery claims based on alleged misrepresentation or fraudulent sale was treated as three years.

    The court found that these claims were filed too late and were consequently barred by limitation.

    3. Earlier suits had been withdrawn

    The record showed that earlier civil suits concerning maintenance and electricity had been filed and later withdrawn. The High Court observed that where a suit is withdrawn without liberty to file afresh, Order XXIII Rule 1 of the Civil Procedure Code prevents a party from bringing another suit on the same cause of action.

    The plaintiffs had not specifically shown that permission had been obtained to preserve their right to refile those claims. The court also endorsed the trial court’s concern that repeated proceedings before different forums amounted to forum hunting.

    4. The suit combined distinct claims of 12 purchasers

    The court stressed that each of the 12 plaintiffs had an individual transaction and a separate cause of action. Their claims could not be treated as one consolidated dispute merely because they related to the same housing project.

    The pleading was therefore held to suffer from misjoinder of parties and causes of action. The claims were also viewed as unquantified, omnibus, and insufficiently specific, particularly because several refund demands were left to be determined later through a proposed local commissioner.

    High Court’s ruling

    Justice Neena Bansal Krishna dismissed Regular First Appeal No. 949/2025 on 11 May 2026. The court affirmed the trial court’s conclusion that the suit was an abuse of the legal process and upheld the dismissal with costs of Rs. 3,000 imposed on each plaintiff.

    Only Lalit Kumar pursued the appeal, while the other original plaintiffs were not parties to the appeal. The court found no merit in the challenge and disposed of the pending applications.

    Key legal takeaway

    The ruling shows that homebuyer grievances, even where numerous and connected to one project, must be pursued before the appropriate forum, within the applicable limitation period, and through precise, properly structured pleadings. A consolidated civil suit cannot be used to revisit matters already adjudicated or pending before RERA, nor to combine unquantified and legally distinct claims of multiple purchasers.

    Listen to this on our #YouTube Channel

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Bombay HC: Builders Cannot Collect More Than 10% of Flat Price Without Registered Sale Agreement β€” RERA Section 13 Compliance Mandatory

    Bombay HC: Builders Cannot Collect More Than 10% of Flat Price Without Registered Sale Agreement β€” RERA Section 13 Compliance Mandatory

    Date: 17.10.2026

    The Bombay High Court has directed Rare Townships Pvt. Ltd. to execute and register a RERA-compliant agreement for sale within four weeks, while treating 4 October 2024 as a tentative possession date pending final determination by the Maharashtra Real Estate Appellate Tribunal.

    Background of the dispute

    The dispute concerns a residential flat in the developer’s Ghatkopar project, originally marketed as β€œRising City” and later registered under RERA as β€œNorth Sea Heights (A-1).”

    The buyers initially received a holding receipt in January 2011 for a different flat. The parties subsequently changed the unit, and a provisional allotment letter dated 30 November 2014 was issued for Flat No. 805 in Building A-1, with a stated consideration of Rs. 1.248 crore.

    The parties ultimately agreed that the buyers had paid Rs. 38.47 lakh by 2016. Despite this payment, no registered agreement for sale was executed. The core disagreements included the unpaid balance, the agreement’s terms, the possession timeline, parking and amenities, and each side’s liability for delay.

    RERA authority’s earlier directions

    In July 2025, MahaRERA partly allowed the buyers’ complaint. It required the developer to execute a registered agreement for sale under Section 13 of the Real Estate (Regulation and Development) Act, 2016, based on the allotment letter.

    MahaRERA also held that:

    • The buyers would pay the outstanding consideration and any applicable interest for delayed payments under the statutory framework.
    • The developer would pay interest for delayed possession from 4 October 2024 until it offered possession with an Occupation Certificate.
    • The parties’ respective payment obligations could be adjusted and set off when possession was delivered.

    The buyers appealed for a more complete RERA-compliant agreement, including parking, amenities, model-agreement protections and safeguards against payment demands or termination before registration.

    Interim tribunal order and developer’s challenge

    The Appellate Tribunal initially directed the developer to provide and execute a RERA-compliant agreement. It also restrained the developer from demanding further money or issuing termination notices until the agreement was executed and registered. A review order corrected the buyers’ payment figure to Rs. 38.47 lakh and corrected the allotment-letter date.

    Rare Townships challenged the interim order in the High Court. Its principal objection was that the Tribunal had effectively decided disputed issues at an interim stage, particularly by requiring the agreement to state a possession date and by excluding interest for alleged payment delays before the agreement’s execution.

    High Court’s reasoning

    The Court emphasized that a registered agreement for sale is not optional once substantial sums have been accepted from a buyer. It noted that both the earlier Maharashtra Ownership Flats Act framework and RERA seek to prevent promoters from accepting significant advances without documenting the parties’ rights and obligations in a registered agreement.

    Under Section 13 of RERA, a promoter cannot accept more than 10% of an apartment’s cost before entering into a registered written agreement for sale. The agreement must cover key matters, including project specifications, payment schedules, the possession date and default interest.

    Here, the Court found that the developer had accepted more than 30% of the agreed consideration without executing the agreement. It therefore upheld the essential requirement to execute a registered, RERA-compliant agreement.

    The Court drew a distinction, however, between requiring an agreement and conclusively determining the contractual possession date. The possession date remained an issue in the buyers’ pending appeal before the Appellate Tribunal. The High Court therefore modified the interim arrangement rather than treating that issue as finally settled.

    Final directions

    The Court disposed of the second appeal with these principal directions:

    • Tentative possession date: The agreement must record 4 October 2024 as the possession date.
    • No final determination: That date is tentative, without prejudice to either side, and remains subject to final adjudication by the Appellate Tribunal.
    • Rectification if required: If the Tribunal changes the possession date, the parties’ rights and liabilities will follow that determination and they must execute a deed of rectification.
    • RERA-compliant agreement: The agreement must comply with Section 13 of RERA and the prescribed model agreement under Maharashtra’s 2017 RERA Rules.
    • Time limit: The developer must execute and register the agreement within four weeks of the judgment.
    • Issues kept open: All remaining disputes, including payment, interest, parking, amenities, compensation and the final possession timeline, remain open before the Appellate Tribunal.

    Why the decision matters

    The ruling reinforces that developers cannot retain substantial buyer payments while postponing the registered agreement for sale. It also confirms that a RERA-compliant agreement must transparently state essential commercial terms, including payment obligations, possession and default consequences.

    At the same time, the judgment preserves procedural fairness: an interim order can secure the statutory agreement and protect buyers from premature demands or termination, but contested issues such as the final possession date must remain available for full appellate adjudication.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Punjab & Haryana HC: Development Authority Is a β€˜Promoter’ Under RERA and Liable for Delayed Possession

    Punjab & Haryana HC: Development Authority Is a β€˜Promoter’ Under RERA and Liable for Delayed Possession

    Date: 26.09.2026


    The Punjab and Haryana High Court has held that a Development Authority falls within the definition of β€œpromoter” under the Real Estate (Regulation and Development) Act, 2016 (RERA) and cannot escape the statutory consequences of delayed possession merely because a commercial site was auctioned on an β€œas is where is” basis or because the allotment terms contained a deemed-possession clause.

    Dismissing two appeals filed by the Bathinda Development Authority, Justice Harkesh Manuja upheld the order of the Real Estate Appellate Tribunal, Punjab granting interest under Section 18 of the RERA Act to allottee Leela Gupta for delayed possession of two SCO sites.

    Background: SCO Sites Purchased Through Auction and Transfer

    • The dispute concerned two SCO sites situated at Civil Lines, Power House Road, Bathinda.
    • Leela Gupta purchased SCO Site No. 1 through an open auction conducted by the Bathinda Development Authority on 5 August 2015. An allotment letter was issued on 1 December 2015 after payment of 20% of the principal amount along with 2% cancer cess.
    • Under the allotment letter, possession was required to be delivered within 90 days.
    • SCO Site No. 2 was not originally allotted to Gupta. She subsequently acquired it by transfer from the original allottees on 4 August 2017. Her grievance was that despite payment according to schedule, possession of the sites was not handed over in time because the necessary development work had not been completed.

    Earlier Proceedings Before PUDA and RERA

    • Gupta initially sought relief from the Estate Officer, Bathinda, contending that interest should not be charged for the period during which the sites were not ready for possession.
    • After her representation was rejected, she approached the High Court through CWP No. 24881 of 2018. The High Court permitted her to submit an appeal-cum-representation to the Chief Administrator, PUDA for a speaking decision.
    • The Chief Administrator subsequently rejected her claim for waiver of interest on instalments but extended the moratorium period for construction, noting that development works in the commercial pocket had been completed on 16 June 2017.
    • Gupta thereafter approached the Real Estate Regulatory Authority, Punjab seeking three reliefs: refund of interest charged on instalments, extension of the non-construction period, and interest under Section 18 of RERA.
    • The Authority dismissed her complaints. On appeal, however, she restricted her claim only to interest for delayed possession under Section 18.

    RERA Appellate Tribunal Awards Interest for Delayed Possession

    • The Real Estate Appellate Tribunal, Punjab allowed Gupta’s appeals on 12 May 2022.
    • For SCO Site No. 1, it awarded interest for delayed possession from 1 March 2016 to 19 October 2017.
    • For SCO Site No. 2, it awarded interest from 4 August 2017 to 19 October 2017 on the amount deposited up to that date, applying Rule 16 of the Punjab State Real Estate (Regulation and Development) Rules, 2017.
    • Bathinda Development Authority challenged those orders before the Punjab and Haryana High Court.

    Development Authority Questions Maintainability of RERA Proceedings

    • The Authority argued that the dispute arose from allotments governed by the Punjab Regional and Town Planning and Development Act, 1995 (PRTPD Act).
    • According to it, after the Chief Administrator passed the order dated 27 May 2019 in exercise of appellate powers under Section 45 of the PRTPD Act, Gupta’s appropriate remedy was to file a revision before the State Government under Section 45(8) rather than initiating proceedings under RERA.
    • The High Court rejected this contention.
    • It noted that Gupta had relinquished her other claims and restricted the dispute before the RERA authorities to the statutory remedy of interest under Section 18 of RERA. Her claim was therefore independently founded on the RERA Act.
    • The Court also noted that the maintainability objection had not been raised by the Development Authority before either the RERA Authority or the Appellate Tribunal and was being advanced for the first time at a belated stage.

    Section 18 RERA Creates Statutory Right to Interest for Delay

    • The High Court examined Section 18 of the RERA Act, which provides remedies where a promoter fails to complete or give possession of an apartment, plot or building according to the agreed terms.
    • Where the allottee does not wish to withdraw from the project, the proviso to Section 18(1) requires the promoter to pay interest for every month of delay until possession is handed over, at the prescribed rate.
    • The issue therefore turned on whether Bathinda Development Authority was a β€œpromoter” and whether there had actually been delay in making the sites ready for possession.

    Development Authority Expressly Covered by Definition of β€˜Promoter’

    • The High Court referred to Section 2(zk)(iii) of the RERA Act, which expressly includes a development authority or other public body within the definition of β€œpromoter” in relation to specified buildings, apartments and plots.
    • The Court therefore held that there was β€œno doubt” that Bathinda Development Authority was covered within the statutory definition of promoter.
    • This finding is important because it confirms that a public development authority cannot seek exemption from RERA’s promoter obligations merely because it is a statutory or State authority rather than a private developer.

    β€˜As Is Where Is’ Clause Does Not Excuse Delayed Development

    • Bathinda Development Authority relied heavily on two provisions in the allotment letter.
    • First, the plot had been offered on an β€œas is where is” basis. Second, the allotment letter stated that possession would be given within 90 days and, if the allottee did not take possession within that period, possession would be deemed to have been handed over on the due date.
    • The High Court was not persuaded.
    • It reasoned that if the β€œas is where is” clause completely absolved the Authority from carrying out development, there would have been no reason for the Authority itself to spend resources and time undertaking development work.
    • The record showed that development of the site was, in fact, the Authority’s responsibility.

    The Court importantly observed that:

    • β€œMere physical possession without any basic amenities would serve no purpose”
    • because construction and commercial activity could not practically be carried out without the necessary basic infrastructure.

    Electricity Is a Basic Amenity; Site Was Ready Only on 19 October 2017

    The date on which the sites could genuinely be treated as ready for possession became a central issue.

    An RTI response showed that:

    • civil and public health works were completed on 16 June 2017;
    • electrical works were completed on 28 April 2017;
    • transformers were installed on 1 March 2017; and
    • electricity supply became available only on 19 October 2017.
    • The Chief Administrator had treated 16 June 2017 as the completion date, apparently without treating actual electricity supply as essential.
    • The High Court disagreed.
    • It held that electricity was a basic amenity necessary for construction activity, particularly because machinery used at a construction site requires power. It therefore affirmed the Appellate Tribunal’s conclusion that the sites were actually ready for possession only on 19 October 2017.

    Extension of Construction Moratorium Was an Indirect Admission of Delay

    • The Court also identified what it considered an inconsistency in the Authority’s stand.
    • The Chief Administrator had extended the three-year moratorium period for construction on the ground that the commercial pocket became ready only after development work was completed.
    • According to the High Court, if there had genuinely been no delay on the Authority’s part, there would have been no need to extend the construction moratorium.
    • The extension was therefore treated as an indirect admission through the Authority’s own conduct that delay had occurred.

    Allottee Cannot Face Penalty for Delay While Promoter Faces No Consequence

    • The High Court also addressed the imbalance that would arise if the Authority’s interpretation were accepted.
    • It observed that an allottee could be required to pay penalty charges for failing to complete construction within the stipulated period. It would therefore be anomalous if there were no corresponding consequences for the promoter’s delay in providing possession, especially when Section 18 of RERA expressly provides a statutory remedy for such delay.

    Supreme Court’s Arifur Rahman Khan v. DLF Southern Homes Applied

    The High Court relied on the Supreme Court’s judgment in:

    Wg. Cdr. Arifur Rahman Khan and Aleya Sultana v. DLF Southern Homes Pvt. Ltd., (2020) 16 SCC 512.

    • The Court referred to the Supreme Court’s recognition that agreements between developers and purchasers often do not operate on an equal footing: stringent obligations imposed on purchasers are frequently not mirrored by equivalent obligations on developers to meet timelines.
    • Bathinda Development Authority argued that Gupta had participated in the auction with her β€œeyes wide open.”
    • The High Court rejected this reasoning, observing that participation in an open auction could not mean that the allottee should have anticipated that the Authority itself would delay development work.
    • The fact that the site had been allotted through an auction did not confer any right upon the Authority to delay development. Once delay occurred, the statutory consequences under RERA had to follow.

    State Development Authority Cannot Claim Preferential Treatment Over Private Promoter

    • The High Court made another significant observation concerning public development authorities.
    • It held that no concession could be claimed by a State Development Authority merely because it was a public body rather than a private promoter.
    • Indeed, the Court observed that the obligation upon the State was greater because it was itself a law-enforcement agency, particularly where it had maximised revenue by disposing of property through an open auction.
    • The ruling therefore places public development authorities squarely within the accountability framework established by RERA where the statutory definition of promoter is attracted.

    Earlier PUDA Order Did Not Bar Section 18 Claim

    • The Authority further argued that the Chief Administrator’s order dated 27 May 2019 had never been challenged and continued to remain in force.
    • The High Court rejected this objection because the earlier proceeding concerned a different relief.
    • The Chief Administrator had rejected Gupta’s request that interest should not be charged on her instalments during the development period.
    • The RERA proceedings, by contrast, concerned her affirmative statutory entitlement to receive interest from the promoter for delayed possession under Section 18.
    • The two issues were therefore legally distinct.

    Other Allottees Taking Possession Earlier Does Not Defeat Statutory Right

    • The Authority also claimed that similarly situated allottees had taken possession earlier.
    • The High Court noted that no material had been placed on record to substantiate this assertion. More importantly, even assuming it to be factually correct, the conduct of other allottees could not extinguish Gupta’s rights arising from the statutory provisions.

    Final Decision: Bathinda Development Authority’s Appeals Dismissed

    • The Punjab and Haryana High Court found no reason to interfere with the Real Estate Appellate Tribunal’s order.
    • Both RERA Appeal No. 6 of 2023 and RERA Appeal No. 12 of 2023 filed by Bathinda Development Authority were dismissed.

    Consequently, Leela Gupta succeeded, and the Appellate Tribunal’s award of delayed-possession interest remained intact:

    SCO SitePeriod for Which Interest Was Awarded
    SCO Site No. 11 March 2016 to 19 October 2017
    SCO Site No. 24 August 2017 to 19 October 2017
    • The interest was to operate on the deposited amount in accordance with the applicable RERA framework and Rule 16 of the Punjab State Real Estate (Regulation and Development) Rules, 2017.

    Key Takeaway

    The judgment establishes three important RERA principles. A Development Authority is expressly covered within the definition of β€œpromoter” under Section 2(zk); an β€œas is where is” or deemed-possession clause cannot automatically defeat the statutory entitlement under Section 18 where the site was not practically ready for possession; and essential infrastructure such as actual electricity supply may be relevant in determining when a commercial site became genuinely ready for possession.

    Most importantly, the High Court made clear that State development authorities cannot claim a more favourable standard than private promoters when RERA obligations apply.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download: