Delhi High Court Says Arbitrators Cannot Turn Penalty Clauses Into Payment Clauses

The Delhi High Court has partly set aside two arbitral awards that required the Delhi Development Authority (DDA) to compensate B.G. Shirke Constructions Technology Private Limited for allegedly excess cement used in M-30 grade concrete, holding that the tribunal created a payment entitlement not supported by the contract.
The dispute arose from conflicting cement clauses
The case concerned two large DDA housing contracts for construction of 24,660 LIG and 7,130 EWS homes in Narela and Rohini using prefabricated technology. DDA awarded the Group I and Group II works to B.G. Shirke in April 2013.
At the centre of the dispute were two contract provisions governing cement consumption in reinforced cement concrete (RCC):
- Clause 9.1.2 referred to the CPWD Specifications, 2009 and IS:456 for minimum cement content. The CPWD specifications set a range of 330 kg to 500 kg per cubic metre, with the final quantity to be determined through the design mix.
- Clause 9.1.3 stated that the minimum cement quantity for βany grade of RCCβ would be 360 kg per cubic metre. It also specified recovery thresholds of 410 kg per cubic metre for M-25 concrete and 428 kg per cubic metre for M-35 concrete.
The contractor had identified this apparent inconsistency during the pre-bid stage and sought clarification twice. DDA replied that the tender provision would prevail. During execution, DDA required a design mix using 410 kg of cement per cubic metre for M-30 concrete. The contractor contended that its rates had been priced on a 330 kg baseline and sought reimbursement for the additional cement.
What the arbitral tribunal awarded
The tribunal found that Clauses 9.1.2 and 9.1.3 conflicted. Applying the principle of contra proferentemβunder which ambiguity in a drafted contract may be construed against its drafterβit treated 330 kg per cubic metre as the relevant baseline.
It distinguished M-30 from M-25 and M-35 because the contract listed specific recovery thresholds only for the latter two grades. The tribunal therefore held that the contractor could recover payment for M-30 cement used above 330 kg per cubic metre.
It awarded the contractor βΉ3,16,78,614 for M-30 concrete work completed up to 30 June 2015. The amount was calculated by treating 80 kg per cubic metre as excess cement and applying a rate of βΉ6 per kg. The tribunal also directed DDA to:
- refund recoveries made in relation to M-30 cement consumption;
- pay βΉ6 per kg for qualifying M-30 cement consumption after 1 July 2015; and
- bear related interest consequences.
The contractorβs claim for additional payment for M-25 concrete was rejected.
High Court: the tribunal could interpret ambiguity, but not rewrite the bargain
DDA challenged both awards under Section 34 of the Arbitration and Conciliation Act, 1996. The Court reaffirmed that it does not sit as an appellate forum over an arbitral award and cannot interfere merely because another contractual interpretation is possible.
However, it emphasized an important limit: an arbitral tribunal must remain within the contractβs terms. It cannot ignore an express provision, invent a payment mechanism, or impose a financial obligation without a contractual or independent legal basis.
The Court accepted that the tribunalβs view of the apparent tension between the two clauses was plausible in relation to M-25 and M-35. The 360 kg figure in Clause 9.1.3 fell within the CPWD range of 330 kg to 500 kg, so the clauses could potentially have been harmonized. Still, the tribunalβs finding of ambiguity was not so implausible as to justify interference on that limited issue.
Why M-30 concrete was treated differently
The Court reached a different conclusion for M-30 concrete. It noted that Clause 9.1.2 specifically referred to M-25 and M-35, while Clause 9.1.3 expressly required at least 360 kg per cubic metre for βany grade of RCC.β That wording necessarily included M-30.
According to the Court, there was therefore no ambiguity that justified extending the 330 kg baseline to M-30. By doing so, the tribunal failed to give effect to the express wording of Clause 9.1.3.
The Court also found that the tribunal had not identified a clause authorizing separate payment for cement consumed above either 330 kg or 360 kg per cubic metre. The contracts were lump-sum agreements, and the requirement to use 410 kg per cubic metre remained within the CPWD-permitted design-mix range of 330 kg to 500 kg.
The absence of an M-30 recovery threshold did not create a corresponding right for the contractor to receive additional payment. In the Courtβs words, a lack of recovery rights against a contractor does not automatically establish a reciprocal payment obligation in its favour.
Recovery rate could not be converted into a payment rate
The Court also rejected the tribunalβs use of the βΉ6-per-kg recovery rate as the basis for compensating the contractor. Clause 1.12 allowed recovery when cement use was deficient; it did not state that the same rate would be payable when consumption exceeded a stated quantity.
Treating a recovery provision as a positive payment obligation effectively reversed the contractual mechanism without any express authorization. The Court held that this amounted to rewriting the agreement and created a financial liability for DDA without a contractual foundation.
Outcome and practical significance
The Court set aside the awards only to the extent they:
- treated 330 kg per cubic metre as the minimum cement content for M-30 concrete;
- awarded βΉ3,16,78,614 for alleged excess M-30 cement consumption up to 30 June 2015;
- directed future M-30 payments at βΉ6 per kg from 1 July 2015;
- required refunds linked to that payment entitlement; and
- granted consequential interest on those reliefs.
All remaining findings of the arbitral awards were left undisturbed, and the Court made no order as to costs.
Key takeaway for construction contracts
The ruling underlines that an arbitral tribunal may resolve genuine contractual ambiguity, but it cannot convert a technical requirement or a recovery clause into an additional payment right unless the contract or another pleaded legal basis supports that result.
For employers and contractors, the decision highlights the importance of clearly aligning design-mix requirements, minimum material content, recovery provisions, and variation-payment clauses before work begins.
Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.
Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.
Source: Delhi High Court