Tag: #IndirectTaxLitigations

  • Madras High Court Affirms RERA Non-Applicability to Pre-2017 Completed Projects

    Madras High Court Affirms RERA Non-Applicability to Pre-2017 Completed Projects

    Date: 03.09.2026

    A recent judgment by the High Court of Judicature at Madras has brought clarity to the rights of homebuyers and the jurisdiction of regulatory authorities under the Real Estate (Regulation and Development) Act, 2016 (RERA). The case, involving R. Santhi Pitchaiya Nattar and Homefinders Housing Ltd, revolved around refund claims, project completion, and the applicability of RERA to projects completed before the Act came into force.

    Background of the Case

    • Parties Involved:
      • Appellant: R. Santhi Pitchaiya Nattar
      • Respondent: Homefinders Housing Ltd
    • Project in Dispute: Apartments 13A and 16B in the ‘Elegant Palm’ project, Aatchikadu Village, Villupuram District.
    • Timeline:
      • Booking and payments made in June 2012.
      • Construction agreement and sale deed executed in June 2012.
      • Dispute arose due to alleged delay in completion and handover.

    Key Issues Raised

    1. Whether the project was exempt from RERA registration under Rule 2(h)(iii) of the Tamil Nadu RERA Rules, 2017.
    2. Whether the appellant was entitled to a refund with interest due to non-completion.
    3. Whether a completion certificate from a private architect sufficed in the absence of a certificate from the competent authority.
    4. The jurisdiction of RERA and its appellate bodies over unregistered or pre-RERA projects.

    Proceedings and Arguments

    • Appellant’s Stand:
      • Paid almost the entire sale consideration by 2012.
      • Alleged non-completion and failure to hand over possession.
      • Sought refund with interest from the developer.
    • Respondent’s Stand:
      • Claimed project completion in 2014 and communication to the buyer.
      • Argued that the buyer failed to pay the final installment and did not take possession.
      • Asserted exemption from RERA as the project was completed before 01.05.2017.

    Orders by Regulatory Authorities

    1. TNRERA (Regulatory Authority):
      • Directed the developer to refund the amount paid by the buyer after deducting certain charges.
    2. TNREAT (Appellate Tribunal):
      • Set aside the TNRERA order, holding that the project was exempt from RERA registration and outside its jurisdiction.

    High Court’s Analysis and Judgment

    • The High Court examined the applicability of RERA and the Tamil Nadu RERA Rules, especially Rule 2(h)(iii), which exempts projects completed before 01.05.2017 from registration.
    • The Court found that:
      • The project was listed as completed before the cut-off date and notified as such by the authorities.
      • The regulatory authority (TNRERA) lacked jurisdiction over the dispute as the project was not required to be registered under RERA.
      • Aggrieved buyers in such cases must seek remedies through civil courts or consumer forums, not RERA.
    • Final Decision: The appeals by the buyer were dismissed, upholding the appellate tribunal’s order.

    Implications of the Judgment

    1. Jurisdictional Clarity: Projects completed before 01.05.2017 and duly notified are outside RERA’s purview in Tamil Nadu.
    2. Remedy for Buyers: Buyers in such projects must approach civil courts or consumer forums for grievances, not RERA.
    3. Importance of Timely Communication: Developers must ensure timely completion and proper communication to avoid disputes.
    4. Documentation: Both buyers and developers should maintain clear records of payments, agreements, and communications.

    Conclusion

    This judgment reinforces the boundaries of RERA’s jurisdiction and provides guidance for both homebuyers and developers regarding disputes in pre-RERA projects. It underscores the importance of understanding the legal framework and seeking appropriate forums for redressal.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Defining Party Autonomy and Judicial Review in Indian Arbitration

    Defining Party Autonomy and Judicial Review in Indian Arbitration

    Date: 03.09.2026

    This article explores the Supreme Court of India’s decision in Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India (NHAI), Civil Appeal No. 4779 of 2019, and its far-reaching impact on arbitration law and contract enforcement in India.

    Background of the Dispute

    1. Project and Contract
      • NHAI invited bids for a four-lane bypass on National Highway 26 in Madhya Pradesh.
      • Ssangyong Engineering & Construction Co. Ltd., a Korean company, won the contract for INR 219 crore.
      • The contract included a price adjustment clause (sub-clause 70.3) for key construction components (cement, steel, plant & machinery, and other materials), based on the Wholesale Price Index (WPI).
    2. Change in WPI Series
      • Initially, price adjustments used the WPI (1993-94 = 100, “Old Series”).
      • In 2010, the Ministry of Industrial Development switched to a new WPI series (2004-05 = 100, “New Series”).
      • Both old and new indices were available for calculation, and payments continued accordingly until 2013.
    3. Policy Circular and Dispute
      • In 2013, NHAI issued a circular introducing a “linking factor” to connect the old and new WPI series, requiring contractors to accept this adjustment with an undertaking.
      • Ssangyong objected, provided only a conditional undertaking, and initiated dispute resolution.

    Arbitration and Court Proceedings

    1. Dispute Adjudication and Arbitration
      • The Dispute Adjudication Board (DAB) recommended applying the linking factor, but one member dissented, supporting Ssangyong’s position.
      • The arbitral tribunal (majority) upheld the use of the linking factor and rejected Ssangyong’s claim. The dissenting arbitrator awarded the full claim to Ssangyong.
    2. Court Challenges
      • Ssangyong challenged the majority award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the award was beyond the scope of arbitration and violated public policy.
      • Both the Single Judge and Division Bench of the Delhi High Court upheld the majority award, citing limited grounds for interference.

    Supreme Court’s Analysis and Ruling

    Key Legal Issues Addressed

    1. Scope of Judicial Review under Section 34
      • The Court clarified that post-2015 amendments, the grounds for setting aside arbitral awards are narrower, focusing on fundamental policy of Indian law and most basic notions of justice or morality.
      • Patent illegality is a ground only for domestic (not international commercial) arbitrations.
    2. Application of Unilateral Circulars
      • The Court held that a unilateral circular (like NHAI’s 2013 circular) cannot alter the contract without the other party’s consent.
      • Imposing a new formula via the circular amounted to creating a new contract, breaching fundamental principles of justice.
    3. Natural Justice and Due Process
      • The majority arbitrators relied on government guidelines not disclosed to the parties, violating Ssangyong’s right to present its case.
      • This procedural lapse was sufficient to set aside the award under Section 34(2)(a)(iii).

    Final Decision

    • The Supreme Court set aside the majority arbitral award and the High Court judgments.
    • Instead of remanding for fresh arbitration (which would cause delay), the Court invoked Article 142 of the Constitution to enforce the minority award in Ssangyong’s favor.
    • Ssangyong was awarded INR 2,01,42,827 plus interest as per the contract.

    Impact and Significance

    1. Reinforcement of Party Autonomy
      • The judgment affirms that contract terms cannot be unilaterally altered by one party or by administrative circulars.
    2. Clarification of Public Policy and Patent Illegality
      • The Court narrowed the scope of “public policy” challenges, aligning Indian law with international standards and reducing judicial interference.
    3. Due Process in Arbitration
      • Awards based on undisclosed evidence or guidelines violate natural justice and are liable to be set aside.
    4. Speedy Dispute Resolution
      • By enforcing the minority award directly, the Court prioritized efficiency and finality in arbitration.

    Conclusion

    The Ssangyong Engineering judgment is a milestone in Indian arbitration jurisprudence. It strengthens the sanctity of contracts, limits judicial intervention, and upholds due process, making India a more arbitration-friendly jurisdiction.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Karnataka High Court Clarifies Advocate General’s Consent in Criminal Contempt: Suo Motu Powers and Procedural Safeguards Explained

    Karnataka High Court Clarifies Advocate General’s Consent in Criminal Contempt: Suo Motu Powers and Procedural Safeguards Explained

    Date: 03.09.2026

    A recent judgment by the Karnataka High Court in CRL.CCC No. 5 of 2025 provides valuable insights into the procedural and legal nuances of criminal contempt proceedings in India. This article explores the background, legal arguments, and the court’s reasoning, offering clarity on the role of Advocate General’s consent and the court’s suo motu powers.

    Background of the Case

    The case originated from a petition filed by New Space Research and Technologies Pvt. Ltd. against several individuals, alleging deliberate and wilful disobedience of a High Court order. The complainant sought criminal contempt proceedings under Article 215 of the Constitution of India and the Contempt of Courts Act, 1971, for non-compliance with a court directive regarding search and seizure operations.

    Key Legal Issue: Is Advocate General’s Consent Mandatory?

    A central question was whether a criminal contempt petition filed by a private party, without the Advocate General’s consent, is maintainable. The accused argued that such consent is a substantive safeguard and a prerequisite under Section 15 of the Contempt of Courts Act, 1971. The complainant countered that the petition merely provided information to the court, which could act on its own motion (suo motu) under Article 215 of the Constitution.

    Legal Framework and Precedents

    Relevant Provisions

    • Article 215 of the Constitution: Empowers every High Court to punish for contempt of itself.
    • Section 15 of the Contempt of Courts Act, 1971: Outlines how criminal contempt can be initiatedβ€”by the court suo motu, by the Advocate General, or by any other person with the Advocate General’s written consent.
    • High Court of Karnataka (Contempt of Court Proceedings) Rules, 1981: Specifies procedures for filing and processing contempt petitions.

    Arguments and Judicial Reasoning

    • The accused relied on Supreme Court decisions (P.N. Duda v. P. Shiv Shanker and Bal Thackrey v. Harish Pimpalkhute) to assert the necessity of Advocate General’s consent for private motions.
    • The complainant cited cases (including Prashant Bhushan v. Alleged Contemnor) to argue that the court can act suo motu based on information received in any legally recognized form, including a petition.
    • The court analyzed the distinction between private motions and information that triggers suo motu action. It emphasized that while consent is mandatory for private motions, the court retains the power to act on its own motion upon receiving information, even if submitted as a petition.

    Court’s Decision and Its Implications

    The High Court concluded that:

    1. Consent of the Advocate General is mandatory for private motions under Section 15(1)(b) of the Act.
    2. However, the court can act suo motu upon receiving information, including through a petition, without such consent.
    3. Procedural Safeguards: The court reiterated that petitions seeking suo motu action should be treated as information and placed before the Chief Justice for consideration, not directly admitted as contempt cases.
    4. Outcome: The court recalled its earlier order overruling objections on maintainability and directed the Registry to treat the petition as information under Rule 7, to be placed before the Chief Justice.

    Practical Takeaways for Legal Practitioners and Litigants

    1. Understand the Distinction: Private parties must obtain Advocate General’s consent for criminal contempt petitions unless they are merely providing information for the court’s consideration.
    2. Follow Proper Procedure: Petitions intended as information for suo motu action should not be styled as regular contempt cases but routed through the administrative process.
    3. Court’s Discretion: The High Court’s inherent powers under Article 215 remain robust, allowing it to act on credible information of contempt, regardless of the source.

    Conclusion

    This judgment clarifies the procedural safeguards and the balance between preventing frivolous contempt petitions and empowering courts to uphold their authority. Legal professionals should carefully assess the mode of initiation and procedural requirements when dealing with criminal contempt matters in the High Courts.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Delhi High Court Mandates Due Process and Notice Before Removal of Registered Trademark for Non-Renewal

    Delhi High Court Mandates Due Process and Notice Before Removal of Registered Trademark for Non-Renewal

    Date: 03.09.2026

    This article explores a significant decision by the Delhi High Court in the matter of Gopal Ji Gupta vs. Union of India, which clarifies the legal procedures and rights concerning the renewal and removal of registered trademarks in India. The judgment not only impacts trademark proprietors but also sets a precedent for the protection of intellectual property rights.

    Background of the Case

    Gopal Ji Gupta, trading as M/s Kiran Textiles, applied for the registration of the trademark “BINACA” under Class 25 on June 15, 1987. The registration process was protracted, with the mark being published in 1995 and finally registered in 1998. The initial validity of the trademark was seven years, making it due for renewal in 1994. However, since the registration was only granted in 1998, the petitioner filed for renewal in 2001, following the then-applicable rules.

    In 2015, upon checking the status of his trademark online, the petitioner discovered that the renewal was overdue. He promptly filed a renewal application, which was rejected by the Registrar of Trademarks as time-barred. The petitioner argued that he had not received the mandatory notice (Form O-3) regarding the expiry and removal of his trademark, as required by law.

    Legal Issues and Arguments

    Petitioner’s Stand

    1. Lack of Mandatory Notice: The petitioner contended that under Section 25(3) of the Trademarks Act, 1999 and Rule 64(1) of the Trademark Rules, 2002, the Registrar must issue a notice (Form O-3) before removing a trademark from the register due to non-renewal.
    2. Right to Renewal: Since no such notice was received, the rejection of his renewal application was argued to be unlawful.
    3. Precedent Cited: The petitioner relied on the Malhotra Book Depot vs. Union of India case, where the court held that removal of a trademark without issuing the prescribed notice is illegal.

    Respondent’s Stand

    1. Delay and Laches: The respondents argued that the renewal application was filed late and that the petition itself was delayed.
    2. No Requirement for Notice: They claimed that since the renewal was not filed within the prescribed period, no notice was necessary.
    3. Alternative Remedy: The respondents also challenged the maintainability of the petition, suggesting that the petitioner should have appealed to the Appellate Board.

    Court’s Analysis and Findings

    The Court addressed two main issues:

    1. Maintainability of the Petition: The Court accepted the petitioner’s argument that the Appellate Board was not fully constituted at the time, making the writ petition maintainable.
    2. Requirement of Notice Before Removal:
      • The Court emphasized that removal of a trademark from the register has significant civil consequences and cannot be done without following the mandatory procedure of issuing a notice in Form O-3.
      • Citing the Malhotra Book Depot case, the Court reiterated that mere expiration of registration does not automatically authorize removal; due process must be followed.
      • The Court also highlighted that intellectual property rights, like tangible property, cannot be taken away without due process of law.

    Judgment and Directions

    The Delhi High Court ruled in favor of the petitioner, holding that:

    • The Registrar of Trademarks cannot remove a trademark from the register without issuing the mandatory notice as per Section 25(3) and the relevant rules.
    • The petitioner’s application for renewal must be considered, subject to payment of late fees and fulfillment of other requirements.
    • Since no third party had applied for the same mark, the petitioner’s rights were further protected.

    Key Takeaways for Trademark Owners

    1. Mandatory Notice: Trademark proprietors must be given a formal notice before their mark is removed for non-renewal.
    2. Due Process: Removal of a trademark without following statutory procedures is illegal and can be challenged in court.
    3. Protection of Rights: Intellectual property rights are protected under the law, and due process must be observed before depriving a proprietor of such rights.
    4. Timely Action: While the law provides safeguards, proprietors should monitor their trademark status and act promptly to avoid complications.

    Conclusion

    The judgment in Gopal Ji Gupta vs. Union of India reinforces the importance of procedural fairness in trademark law. It ensures that trademark owners are not deprived of their rights without due notice and legal process, thereby strengthening the framework for intellectual property protection in India.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • Delhi High Court- Customs Department Cannot Enforce Pre-Insolvency Claims Not Submitted During CIRP

    Delhi High Court- Customs Department Cannot Enforce Pre-Insolvency Claims Not Submitted During CIRP

    Date: 03.09.2026

    The Delhi High Court recently delivered a significant judgment in the case of Jaiprakash Associates Limited vs. The Office of the Commissioner of Customs Air Cargo Complex Import & Anr., addressing the interplay between customs liabilities and the Insolvency and Bankruptcy Code, 2016 (IBC). This article provides a detailed analysis of the case, its background, legal arguments, and the broader implications for insolvency proceedings and statutory dues in India.

    Background of the Case

    • Import Transaction: On 15 September 2023, Jaiprakash Associates Limited (JAL) imported Digital and Network Video Recorders, availing a concessional customs duty rate.
    • Customs Dispute: The Customs Department later alleged that the goods were not eligible for the concessional rate, raising a demand for differential duty, interest, and penalty.
    • Insolvency Proceedings: Meanwhile, insolvency proceedings against JAL commenced on 3 June 2024, with a public announcement inviting creditor claims. The Customs Department did not submit any claim during the Corporate Insolvency Resolution Process (CIRP).
    • Resolution Plan: The Committee of Creditors approved a Resolution Plan by Adani Enterprises Limited, which was subsequently approved by the National Company Law Tribunal (NCLT) on 17 March 2026. The plan explicitly extinguished all pre-CIRP claims not submitted during the process.
    • Customs Order: Despite being informed of the approved Resolution Plan, the Customs Authority passed an order on 2 June 2026, confirming the demand against JAL.

    Key Legal Issues

    1. Whether customs liabilities arising from pre-CIRP transactions can be enforced after approval of a Resolution Plan if the claim was not submitted during CIRP.
    2. Whether the Customs Department’s failure to submit a claim during CIRP extinguishes its right to recover dues post-approval of the Resolution Plan.

    Arguments Presented

    Petitioner (Jaiprakash Associates Limited)

    • The customs liability pertained to a period before the insolvency commencement date.
    • The Customs Department, as an operational creditor, failed to submit its claim during CIRP.
    • Section 31(1) of the IBC and the Supreme Court’s decision in Ghanashyam Mishra & Sons (P) Ltd. v. Edelweiss Asset Reconstruction Co. Ltd. establish that unfiled pre-CIRP claims are extinguished upon approval of the Resolution Plan.
    • The Resolution Plan, binding on all stakeholders including government authorities, specifically extinguished such claims.

    Respondents (Customs Department)

    • The Customs Act allows determination of customs duty, interest, and penalty, regardless of CIRP.
    • The customs liability was not shown to have been considered in the Resolution Plan.
    • The pendency of CIRP was only brought to their notice at the final hearing stage.
    • An appeal remedy exists under the Customs Act.

    Court’s Analysis and Findings

    • Wide Definition of “Claim”: The IBC defines “claim” broadly, covering all rights to payment, whether adjudicated or not. The customs liability, though not quantified before CIRP, was a claim under the IBC.
    • Public Announcement Mechanism: The IBC requires a public announcement for creditors to submit claims. The Customs Department’s failure to respond to this announcement meant its claim was not considered in the Resolution Plan.
    • Binding Nature of Resolution Plan: Section 31(1) of the IBC, especially after the 2019 amendment, makes the approved Resolution Plan binding on all creditors, including government authorities. The Supreme Court has clarified that unfiled claims are extinguished upon approval.
    • IBC Prevails Over Other Laws: Section 238 of the IBC gives it overriding effect in case of inconsistency with other laws, including the Customs Act.
    • No Exception for Statutory Dues: The Court rejected the argument that statutory dues enjoy a special status outside the IBC framework, citing recent Supreme Court jurisprudence.
    • No Recovery Post-Approval: The Customs Department could not enforce a pre-CIRP claim after the Resolution Plan’s approval, as it had not participated in the CIRP.

    Judgment and Impact

    • The High Court quashed the Customs Department’s order confirming the demand against JAL.
    • The judgment reinforces that all creditors, including government authorities, must submit their claims during CIRP or risk extinguishment upon approval of the Resolution Plan.
    • The decision upholds the IBC’s objective of providing a “clean slate” to successful resolution applicants and ensures finality in insolvency proceedings.

    Key Takeaways for Stakeholders

    1. Government Authorities as Creditors: Statutory authorities must actively participate in CIRP and submit claims within prescribed timelines.
    2. Resolution Applicants: Can rely on the finality of the Resolution Plan and are protected from undisclosed or unfiled pre-CIRP claims.
    3. Corporate Debtors: Are not liable for pre-CIRP claims not included in the Resolution Plan post-approval.
    4. Legal Certainty: The judgment provides clarity and certainty for all stakeholders in insolvency proceedings.

    Conclusion

    The Delhi High Court’s decision in the Jaiprakash Associates Limited case is a landmark in harmonizing the IBC with other statutory regimes. It underscores the importance of timely claim submission by all creditors and affirms the supremacy of the IBC in insolvency matters, ensuring that successful resolution applicants are not burdened with legacy liabilities outside the Resolution Plan.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • Gujarat High Court Restores 18% Contractual Interest Rate for Homebuyers in RERA Refund Dispute

    Gujarat High Court Restores 18% Contractual Interest Rate for Homebuyers in RERA Refund Dispute

    Date: 02.09.2026

    A recent judgment by the Gujarat High Court has clarified the calculation of interest rates in real estate disputes under the Real Estate (Regulation and Development) Act (RERA). This article explores the background, legal provisions, and implications of the case involving Ramsingh Baldharisingh Pal & Ors. versus M/s. Baghel Construction & Ors., focusing on the correct application of interest rates when promoters default on handing over possession.

    Case Background

    • Parties Involved:
      • Appellants: Ramsingh Baldharisingh Pal & others (allottees)
      • Respondents: M/s. Baghel Construction & others (promoters/builders)
    • Project: Shiv Krupa Residency
    • Issue: The promoters failed to hand over possession of flats by the agreed date (31.12.2019). The allottees sought cancellation of the contract and refund of their payments.

    Chronology of Events

    1. Complaint to RERA:
      • Allottees paid Rs. 15,25,000 to the promoters.
      • RERA ordered refund of Rs. 12,05,941 with 18% interest from the payment date, plus Rs. 30,000 as costs.
    2. Promoters’ Appeal:
      • Promoters appealed to the Gujarat Real Estate Appellate Tribunal, which reduced the interest rate from 18% to 9% but upheld the refund and costs.
    3. High Court Appeal:
      • Allottees challenged the reduction in interest rate before the Gujarat High Court.

    Legal Provisions Examined

    Rule 16 of Gujarat RERA Rules, 2017

    • Rule 16(1):
      • The interest rate for defaults is the contractual rate agreed between promoter and allottee.
      • If no rate is agreed, the rate is the State Bank of India MCLR plus 2%.
      • The rate must be equal for both parties in case of default.
    • Section 2(za) of the Act:
      • Reinforces that the interest rate for default by either party must be the same.

    High Court’s Analysis and Decision

    • The High Court found that the Tribunal erred by applying the default statutory rate (MCLR + 2%) instead of the contractual rate.
    • The agreement between the parties specified 18% interest for default by the allottee; thus, the same rate applies if the promoter defaults.
    • The Court quashed the Tribunal’s order reducing the rate to 9% and restored the RERA Authority’s order of 18% interest.

    Key Takeaways for Homebuyers and Promoters

    1. Contractual Rate Prevails:
      • If the agreement specifies an interest rate for default, that rate applies to both parties.
    2. Statutory Rate Applies Only in Absence of Agreement:
      • If no rate is agreed, the statutory rate (SBI MCLR + 2%) is used.
    3. Equality Principle:
      • The law ensures neither party is advantaged or disadvantaged by different interest rates in case of default.

    Implications

    • For Homebuyers:
      • Strengthens the position of allottees seeking refunds for delayed possession.
      • Ensures fair compensation aligned with contractual terms.
    • For Promoters:
      • Highlights the importance of clear contractual terms.
      • Promoters must be aware that the same interest rate applies to them in case of default.

    Conclusion

    This judgment reinforces the principle of parity in interest rates under RERA and provides clarity for both homebuyers and developers. It underscores the importance of adhering to contractual terms and ensures that justice is served in real estate disputes involving delayed possession and refunds.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Bombay High Court’s Analysis of Arbitral Award Challenge under Section 34 of the Arbitration and Conciliation Act, 1996 in a Cotton Supply Dispute

    Bombay High Court’s Analysis of Arbitral Award Challenge under Section 34 of the Arbitration and Conciliation Act, 1996 in a Cotton Supply Dispute

    Date: 02.09.2026

    This article examines the Bombay High Court’s judgment in the arbitration dispute between J. S. Cotton Industries and C. A Galiakotwala & Company Pvt. Ltd., both members of the Cotton Association of India. The case centers on the non-delivery and invoicing back of cotton, the arbitral process under the Association’s Byelaws, and the legal scrutiny of the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

    Background of the Dispute

    1. Contract and Non-Delivery
      • On 11 August 2010, the parties entered into a contract for the supply of 600 bales of cotton, with delivery scheduled between 28 November and 5 December 2010.
      • J. S. Cotton Industries (the Petitioner) failed to deliver the cotton within the agreed period, despite repeated reminders from the Respondent.
      • The Respondent warned that failure to deliver would result in β€œinvoicing back” the cotton at the prevailing market rate, as per the Association’s Byelaws.
    2. Invoicing Back and Arbitration
      • After continued non-delivery, the Respondent applied to the Association to fix the invoice back rate, which was set at Rs. 44,800 per candy as of 13 May 2011.
      • The Respondent issued a debit note for Rs. 41,58,948 plus interest, which the Petitioner did not pay, leading to arbitration.
      • The Sole Arbitrator initially awarded a lower amount based on a different date, but both parties appealed to the Board of Directors of the Association.
      • The Board modified the award, granting the Respondent the full claimed amount with interest.

    Grounds of Challenge by the Petitioner

    The Petitioner challenged the arbitral award in the Bombay High Court on several grounds:

    1. Breach of Natural Justice
      • Alleged that the invoicing back procedure was not properly followed and that key documents (such as the rate fixation report) were not shared, denying the Petitioner the right to appeal the rate.
    2. Procedural Irregularities
      • Claimed that the Respondent did not submit necessary supporting documents with the Statement of Claim.
      • Argued that the contract period was not validly extended and that the invoicing back was based on an incorrect date.
    3. Substance of the Claim
      • Contended that the Respondent sought delivery of a different type of cotton than what was contracted.
      • Asserted that the Respondent should have invoked a different Byelaw (No. 74) for invoicing back.

    Respondent’s Defense

    The Respondent countered that:

    • Both parties were aware of the Byelaws and the weekly published rates.
    • The Petitioner was repeatedly notified of the consequences of non-delivery.
    • The Board’s decision was based on a plausible interpretation of the evidence and Byelaws.
    • The type of cotton demanded was consistent with the contract, as clarified by the Association’s standards.

    Court’s Analysis and Findings

    1. Scope of Judicial Review
      • The Court reiterated that interference with arbitral awards under Section 34 is limited to exceptional circumstances, such as fraud, corruption, or violation of public policy.
    2. Natural Justice and Byelaw Procedures
      • The Court found that Byelaw No. 34A provides a self-contained procedure for price fixation and does not require the Committee to share reports or documents with the parties.
      • The right to appeal the rate fixation was available but not exercised by the Petitioner.
    3. Merits of the Dispute
      • The Board’s findings on the type of cotton and the date for invoicing back were supported by the contract and correspondence.
      • The Court declined to reappreciate evidence, emphasizing the finality of arbitral decisions unless there is a clear violation of law or procedure.
    4. Outcome
      • The petition was dismissed, upholding the arbitral award in favor of the Respondent.
      • The Court ordered the release of any deposited amounts and disposed of interim applications.

    Key Takeaways for Businesses and Legal Practitioners

    1. Importance of Contractual Compliance
      • Non-fulfillment of contractual obligations, especially in commodity trades, can lead to significant financial liabilities through mechanisms like invoicing back.
    2. Understanding Association Byelaws
      • Members of trade associations must be familiar with dispute resolution and price fixation procedures, as these can override general contract law principles.
    3. Limited Scope for Challenging Arbitral Awards
      • Courts will not interfere with arbitral awards on merits unless there is a clear breach of fundamental legal principles or public policy.
    4. Procedural Diligence
      • Parties must exercise their rights (such as appeals) within the prescribed timelines and cannot later claim prejudice if they fail to do so.

    Conclusion

    The J. S. Cotton Industries case underscores the robustness of arbitral processes under trade association byelaws and the judiciary’s reluctance to interfere with well-reasoned arbitral awards. For businesses, it highlights the need for timely compliance, diligent documentation, and a thorough understanding of industry-specific dispute mechanisms.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • High Court of Gujarat on Conditional Release of Seized Vehicle Under NDPS Act

    High Court of Gujarat on Conditional Release of Seized Vehicle Under NDPS Act

    Date: 02.09.2026

    A recent order from the High Court of Gujarat at Ahmedabad addresses the release of a vehicle seized in connection with a narcotics case. This article provides a detailed overview of the case, the legal reasoning behind the court’s decision, and the implications for similar cases involving seized property under the Narcotic Drugs and Psychotropic Substances Act (NDPS Act).

    Background of the Case

    • Case Title: Anwarhusain @ Zandu Allanur Lakhara vs. State of Gujarat
    • Court: High Court of Gujarat, Ahmedabad
    • Vehicle Involved: Maruti Omni (Registration No. GJ-20-A-9287)
    • Context: The vehicle was seized by police in connection with an FIR registered under the NDPS Act, alleging its use in transporting contraband.

    Legal Arguments Presented

    1. Petitioner’s Argument:
      • Sought release of the seized vehicle by invoking the court’s extraordinary jurisdiction under Articles 226 and 227 of the Constitution and Section 497 of the Bharatiya Nagarik Suraksha Sanhita, 2023 (BNSS).
      • Emphasized the court’s wide powers to grant such relief.
    2. State’s Opposition:
      • Argued that the vehicle was used in the commission of an NDPS Act offence and should be confiscated, not released.
      • Cited the Supreme Court’s decision in Bishwajit Dey vs. State of Assam (2025 INSC 32) to support the bar on release under Section 60 of the NDPS Act.

    Court’s Analysis and Reasoning

    • The court clarified that mere use of a vehicle in an NDPS offence does not automatically bar its release.
    • Jurisdiction under Section 451 of the Criminal Procedure Code (Cr.P.C.) and Section 60 of the NDPS Act remains intact for considering release applications.
    • The court noted the absence of direct evidence that contraband was seized from the vehicle itself, relying only on statements from co-accused.
    • The court referenced the Supreme Court’s guidance in Sunderbhai Ambalal Desai vs. State of Gujarat (2002) 10 SCC 283, emphasizing the need to avoid deterioration of seized vehicles during prolonged trials.

    Order and Conditions for Release

    The High Court allowed the petition and directed the trial court to release the vehicle, subject to strict conditions:

    1. Solvent Surety: The petitioner must provide a surety equivalent to the vehicle’s value as stated in the FIR or panchnama.
    2. Undertaking: The petitioner must undertake not to transfer, change the identity, or alter the color of the vehicle until the trial concludes.
    3. Production on Demand: The vehicle must be produced before the trial court whenever required.
    4. Future Offences: If the vehicle is involved in any subsequent offence, it will be confiscated.
    5. Authority’s Rights: The order does not prevent the trial court from initiating confiscation or auction proceedings if necessary.
    6. Documentation: Police must photograph the vehicle from all sides and prepare a panchanama before release, with these documents forming part of the charge sheet.
    7. RTO Notification: The order must be sent to the relevant RTO to record the restriction on transfer until the trial’s conclusion.

    Implications and Takeaways

    • Legal Precedent: The order reinforces that courts retain discretion to release seized vehicles under the NDPS Act, especially when direct evidence of contraband recovery from the vehicle is lacking.
    • Protection of Property: The decision balances the need to preserve evidence with the rights of property owners, preventing unnecessary deterioration of vehicles during lengthy legal proceedings.
    • Stringent Safeguards: The imposed conditions ensure that the vehicle remains available for trial and is not misused or disposed of improperly.

    Conclusion

    This High Court order provides important guidance for handling seized vehicles in narcotics cases. It underscores the judiciary’s role in protecting property rights while upholding the law, and sets out clear procedures and safeguards for the conditional release of such property during ongoing trials.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • Delhi High Court Orders Restoration of ‘BLUE CHIP’ Trademark to Mehta Cosmetics After Procedural Lapse by Registrar

    Delhi High Court Orders Restoration of ‘BLUE CHIP’ Trademark to Mehta Cosmetics After Procedural Lapse by Registrar

    Date: 02.09.2026

    The Delhi High Court delivered a significant judgment in the case of Amrit Singh Mehta Trading as Mehta Cosmetics vs. Controller General of Patents, Designs and Trade Marks. The case revolved around the removal of the ‘BLUE CHIP’ trademark from the register due to alleged non-renewal, raising important questions about procedural fairness and statutory obligations under the Trade Marks Act, 1999.

    Background of the Case

    • Trademark Application and Registration:
      • The petitioner, Amrit Singh Mehta, filed an application for the ‘BLUE CHIP’ trademark (Class 03) on July 21, 1992.
      • The mark was registered on August 3, 2005, after a long delay of 13 years.
      • However, the petitioner never received the registration certificate.
    • Issue of Renewal and Removal:
      • The renewal date, based on the application, was July 21, 2002, but registration was granted only in 2005.
      • Due to non-filing of the renewal application (as the petitioner was unaware of the registration), the trademark was removed from the register and marked as expired in June 2010.
    • Petitioner’s Efforts:
      • The petitioner made several attempts to obtain information through RTI applications.
      • The Trade Marks Registry confirmed registration but could not provide evidence of dispatching the certificate or renewal notices.

    Legal Arguments

    • Petitioner’s Stand:
      • The petitioner argued that under Rule 64(3) of the Trade Marks Rules, 2002, when registration occurs after the renewal date, the proprietor is entitled to a six-month window from the actual date of registration to apply for renewal.
      • Since the registration certificate was never received, the petitioner was deprived of the opportunity to renew.
      • The Registrar failed to send the mandatory notice (Form-O2) before removing the mark, violating Section 25(3) of the Trade Marks Act.
    • Respondent’s Stand:
      • The respondent (Trade Marks Registry) claimed that records were not traceable due to the passage of time and could not confirm dispatch of the certificate or notices.

    Court’s Analysis and Findings

    • The court found that:
      1. The petitioner did not receive the registration certificate, a fact unrefuted by the respondent.
      2. The Registrar failed to send the mandatory renewal notice (Form-O2) before removal.
      3. Rule 64(3) entitled the petitioner to a six-month renewal window from the date of registration, which was missed due to lack of communication.
      4. Removal of the trademark without following statutory procedure was unjustified.
    • The court cited several precedents, emphasizing that removal of a trademark must be preceded by strict compliance with procedural requirements, including notice to the proprietor.

    Judgment and Directions

    • The Delhi High Court ruled in favor of the petitioner:
      1. Directed the restoration and reinstatement of the ‘BLUE CHIP’ trademark registration.
      2. Allowed the petitioner to file a renewal application within six weeks.
      3. Ordered the respondent to process the renewal if all formalities are completed.

    Significance of the Judgment

    This judgment reinforces the importance of procedural safeguards for trademark proprietors. It clarifies that:

    • Statutory notices and communication are mandatory before removal of a trademark.
    • Proprietors must not be penalized for administrative lapses beyond their control.
    • The Registrar’s obligations under the Trade Marks Act and Rules are to be strictly enforced.

    Conclusion

    The decision in Mehta Cosmetics sets a strong precedent for trademark law in India, ensuring that rights of proprietors are protected against procedural lapses by authorities. It highlights the judiciary’s commitment to upholding statutory rights and due process in intellectual property matters.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • Karnataka High Court Orders Retrial in Dowry Death and Murder Case: Focus on Investigation Lapses, Medical Evidence, and Judicial Duties

    Karnataka High Court Orders Retrial in Dowry Death and Murder Case: Focus on Investigation Lapses, Medical Evidence, and Judicial Duties

    Date: 02.09.2026

    This article examines a significant judgment delivered by the High Court of Karnataka in August 2026, addressing criminal appeals and a revision petition related to dowry harassment, alleged murder, and procedural lapses in investigation. The case revolves around the deaths of Madhu and her young son Likhith Gowda in 2004, raising critical questions about the handling of dowry-related crimes, the role of investigative agencies, and the responsibilities of medical professionals in post-mortem analysis.

    Case Background

    • Incident: On October 6, 2004, Madhu and her son were found dead in their matrimonial home. The initial police investigation concluded suicide for Madhu (by hanging) and murder by throttling for her son.
    • Allegations: The complainant (Madhu’s father) alleged dowry harassment, physical and mental cruelty, and accused the police of failing to properly investigate the possibility of murder under Section 302 of the Indian Penal Code (IPC).
    • Legal Proceedings:
      1. Criminal Revision Petition (CRL.RP No. 83/2013): Challenged the discharge of accused for murder (Section 302 IPC) and sought continuation of trial.
      2. Criminal Appeals (CRL.A No. 740/2018 & 450/2018): Filed by the State and the complainant against the acquittal of the accused for dowry harassment, abetment of suicide, and dowry death under IPC Sections 498A, 304B, 306, and Dowry Prohibition Act Sections 3, 4, 6.

    Key Issues Examined by the Court

    1. Whether the trial court erred in discharging the accused for murder (Section 302 IPC).
    2. Whether the acquittal for dowry-related offences was justified.
    3. Whether the investigation and medical examination were defective, leading to miscarriage of justice.

    Court’s Analysis and Findings

    1. Investigation and Procedural Lapses

    • The court found that both the police and the Crime Investigation Department (COD) failed to properly investigate the possibility of murder, especially regarding the death of the child, and did not invoke Section 302 IPC as warranted by the evidence.
    • The post-mortem reports and inquest findings showed inconsistencies, particularly regarding the nature and location of injuries, the ligature marks, and the timeline of death.
    • The court criticized the reliance on a ‘death note’ found 13 days after the incident, questioning its authenticity and the lack of proper forensic analysis.

    2. Medical Evidence and Forensic Gaps

    • The post-mortem reports failed to explain key injuries and did not clarify whether the deaths were homicidal or suicidal.
    • The court highlighted the need for expert forensic opinion, especially when ante-mortem injuries and suspicious circumstances are present.
    • The judgment emphasized the duty of medical professionals to provide clear, detailed, and scientifically sound reports.

    3. Role of the Judiciary

    • The court underscored the active role judges must play in criminal trials, including questioning witnesses and seeking clarifications to uncover the truth.
    • It criticized the trial court for focusing excessively on minor discrepancies and delay in lodging the complaint, rather than the substantive evidence of dowry harassment and suspicious deaths.

    4. Dowry Harassment and Presumptions

    • The court noted that the evidence established a pattern of dowry demand and harassment, which, under Sections 113A and 113B of the Indian Evidence Act, creates a presumption against the accused when a woman dies within seven years of marriage under suspicious circumstances.
    • The trial court’s failure to apply these presumptions was deemed a serious error.

    Final Orders and Directions

    1. Setting Aside Acquittal: The High Court set aside the trial court’s acquittal and discharge orders, remanding the case for reconsideration and framing of charges under Section 302 IPC.
    2. Re-examination: Directed the trial court to re-examine the investigating officers and doctors, and if necessary, seek expert forensic opinion.
    3. Time-bound Trial: Ordered the trial court to dispose of the matter within four months, with day-to-day hearings.
    4. Systemic Reforms:
      • Directed the Registrar General to communicate the judgment to police and health authorities for training on proper investigation and post-mortem procedures.
      • Mandated compliance reporting to ensure accountability.

    Broader Implications

    • For Law Enforcement: The judgment serves as a stern reminder of the need for thorough, unbiased, and scientifically sound investigations in cases of unnatural deaths, especially those involving women and children.
    • For Medical Professionals: Highlights the critical role of accurate and comprehensive post-mortem reports in the criminal justice process.
    • For the Judiciary: Reinforces the proactive duty of judges to seek the truth and not merely act as passive arbiters.
    • For Society: Reaffirms the seriousness with which dowry-related crimes must be treated and the legal presumptions that protect victims.

    Conclusion

    This landmark judgment not only addresses the specific lapses in the case at hand but also sets important precedents for handling dowry deaths, suspicious suicides, and the responsibilities of investigators and medical professionals. It calls for systemic reforms and greater vigilance to ensure justice for victims and accountability for those entrusted with upholding the law.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download: