
Aadrikaa Legal Services (ALS)- Law I Litigation I Arbitration
Date: 15.09.2026
Supreme Court: Developer Cannot Be Penalised for NOIDAβs Failure to Provide Promised 45-Metre Access Road
This Short Article has been prepared & written by Advocate Narendra Singh. The views expressed are based on his interpretation of the law. He can be reached at his email id amitnaren@outlook.com .

The Supreme Court has dismissed appeals filed by the New Okhla Industrial Development Authority (NOIDA) and upheld the grant of βZero Periodβ benefit to M/s Sunshine Trade Tower Pvt. Ltd., holding that a development authority cannot deny contractual and policy relief to a developer when its own failure to provide adequate and legitimate access materially prevents development of the allotted commercial plot.
In New Okhla Industrial Development Authority & Ors. v. M/s Sunshine Trade Tower Private Limited & Anr., Civil Appeal Nos. 10900-10902 of 2025, 2026 INSC 975, a Bench comprising Justices Pamidighantam Sri Narasimha and Alok Aradhe upheld the Allahabad High Court judgment granting Zero Period benefit to the developer. The Supreme Court delivered its judgment on 8 September 2026.
The Court importantly held that a policy such as NOIDAβs Zero Period Policy should not be interpreted in the same manner as a statute. Its provisions must instead be construed in light of the policyβs purpose and broader objective.
βΉ133.86 Crore Commercial Plot Allotted in Noida
- The dispute arose from a scheme launched by NOIDA on 22 September 2011 for allotment of commercial plots to builders and developers.
- Sunshine Trade Tower emerged as the successful developer, following which a lease deed dated 11 January 2012 was executed for Plot No. 5-A, Sector 94, Noida, for a total consideration of approximately βΉ133.86 crore. Possession was handed over on the same date.
- Under the approved site plan, the commercial plot had a 45-metre-wide Front Road and a 24-metre-wide Side Road. The developer was to construct a commercial complex comprising facilities such as shopping malls, showrooms, retail outlets, hotels, restaurants and offices.
- The developer, however, claimed that proper construction could not proceed because the 45-metre Front Road was encroached upon while the 24-metre Side Road was sandy, unpaved and non-motorable.
NGT Order Also Stopped Construction Near Okhla Bird Sanctuary
- Another obstacle emerged in September 2013 when the National Green Tribunal directed stoppage of construction within 10 kilometres of the Okhla Bird Sanctuary.
- Since Sunshine Trade Tower’s plot was located within approximately 600 metres of the sanctuary boundary, construction was stopped.
- The restriction continued until the Central Government issued a notification on 19 August 2015 specifying the relevant eco-sensitive limits. Even after removal of this restriction, however, the developer contended that full-fledged construction remained impossible because the 45-metre road continued to be encroached and the 24-metre road remained incomplete.
What Is NOIDAβs βZero Period Policyβ?
- NOIDA formulated its Zero Period Policy on 28 March 2016 to deal with projects that could not progress because of circumstances beyond the developer’s control.
- Among other situations, Clause 5 contemplated relief where possession and lease had been completed but there was no access road to the allotted land, preventing construction or development.
- The policy also provided for rescheduling instalments falling within the Zero Period and stipulated that penal interest would not be charged for the relevant period.
- Sunshine consequently sought Zero Period benefits both for the NGT restraint and for NOIDAβs failure to provide proper access roads.
- NOIDA initially granted limited benefit relating to the NGT restriction but did not accept the developerβs wider claim concerning access to the plot.
NOIDAβs Own Tehsildar Found 45-Metre Road Blocked
- A crucial piece of evidence was a report submitted by NOIDAβs Tehsildar on 14 February 2019.
- The report found that the land earmarked for the 45-metre road fell in Khasra No. 684, was recorded as Abadi land, had not been acquired by NOIDA and continued to be occupied by villagers.
- The Tehsildar consequently recorded that the access road to the commercial plot was blocked.
- Despite this report, NOIDA rejected the developerβs request for Zero Period benefit, maintaining that adequate access was available.
UPRERA Also Recorded NOIDAβs Failure to Provide 45-Metre Road
- The dispute subsequently reached UPRERA. Although the developer’s complaint was rejected as not maintainable and it was asked to pursue other statutory remedies, UPRERA’s technical inspection recorded important factual findings.
- It found that the 24-metre road was completed only in 2020, nearly eight years after allotment, while the promised 45-metre road had still not been constructed because of existing habitation.
- UPRERA recorded that NOIDA had failed to provide the 45-metre-wide approach road contemplated under the lease arrangement.
State Government Partly Granted Relief
- The matter thereafter went through revisional proceedings before the Uttar Pradesh Government.
- In its second revisional order dated 14 September 2022, the State Government found that the 45-metre road was blocked by encroachment and that its non-availability affected the project’s commercial viability.
- It granted the developer waiver of penal interest and a one-year COVID-related extension and directed NOIDA to take consequential steps.
- The State Government specifically recognised that the commercial project had been designed on the assumption that the 45-metre road would constitute the principal access/frontage. Its absence meant that the projectβs layout and commercial attractiveness would have to be reconsidered.
NOIDA Raised βΉ100.39 Crore Demand
- The dispute continued, and NOIDA ultimately issued a demand notice dated 23 February 2024 seeking payment of approximately βΉ100.39 crore towards principal and premium, without interest.
- The developer challenged this demand as well as NOIDAβs refusal to sanction its revised building plan before the Allahabad High Court.
- The High Court held that the cumulative circumstances prevented adequate access to the plot and concluded that Sunshine Trade Tower was entitled to Zero Period benefit.
- It directed NOIDA to make a fresh calculation after granting Zero Period relief, raise a revised demand, and thereafter approve the revised building plan subject to statutory formalities.
- NOIDA challenged that judgment before the Supreme Court.
NOIDA: Some Access Was Available, So Zero Period Could Not Apply
- Before the Supreme Court, NOIDA argued that Clause 5 of the Zero Period Policy should be interpreted strictly.
- According to the Authority, relief was available only where there was absolutely no physical access to the allotted land and construction was therefore impossible.
- NOIDA maintained that Sunshine had some access through the 24-metre road and portions of the 45-metre road and had even undertaken construction activity. It also contended that the developer’s own excavation contributed to the delay in completion of the side road.
- The developer countered that the real issue was not whether it could somehow physically reach the property from one corner, but whether the commercial project could be developed in accordance with the sanctioned plan.
- The promised 45-metre road was the project’s principal frontage. Its permanent non-availability required fundamental alterations to the building’s frontage, orientation, setbacks, entry and exit points and overall configuration.
Supreme Court: Policy Cannot Be Interpreted Like a Statute
- Rejecting NOIDA’s narrow construction, the Supreme Court laid down an important principle concerning interpretation of government and development policies.
- The Court held that provisions of a policy such as the Zero Period Policy βare not to be interpreted like the provisions of a statute.β
- Instead, courts must consider both the immediate purpose of the particular clause and the broader objective of the policy.
- The Supreme Court found that Clause 5 was intended to ensure that a developer received easy, effective and legitimate access to the allotted property so that construction could meaningfully proceed.
- The mere fact that the developer could somehow obtain limited access could therefore not absolve NOIDA of its obligation.
- The Court held that where adequate access had not been provided for reasons attributable to NOIDA, Zero Period benefit could not be denied merely because βsome access was available.β
Supreme Court Finds NOIDA Failed to Provide Promised 45-Metre Road
- The Supreme Court examined five important official documents: the Tehsildar’s report, UPRERA order, Additional CEO’s inspection report, State Government’s revisional order and Deputy Collector’s report.
- The cumulative effect of these documents, the Court said, left βno doubtβ that the 45-metre Front Road was never made available to Sunshine by NOIDA.
- The Court further observed that NOIDA, as the statutory development authority, possessed the means to remove encroachments and open the access road but had failed to do so.
Frontage Is Not Merely an Architectural Issue
- The judgment contains significant observations concerning the commercial importance of frontage, accessibility and elevation in real-estate development.
- The Supreme Court observed that frontage and elevation are not merely architectural aesthetics; they are important determinants of a property’s commercial value and marketability.
- For commercial developments in particular, visibility and accessibility directly affect footfall, branding and business prospects.
- Uncertainty concerning frontage can therefore affect project viability, investor confidence and the expectations of purchasers and commercial occupants.
Changing From 45-Metre to 24-Metre Frontage Fundamentally Affected Project
- Applying those principles, the Court observed that Sunshine’s original sanctioned plan treated the 45-metre road as the project’s principal frontage.
- Since that road could no longer realistically be provided, the 24-metre Side Road would have to become the new frontage.
- This was not a minor internal modification. It required reconsideration of setbacks, building orientation, entry and exit points, permissible configuration and other planning parameters.
- The Court held that changing the frontage from 45 metres to 24 metres directly affected the development potential and commercial attractiveness of the property.
Developer Cannot Be Made Liable for NOIDAβs Own Failure
- The Supreme Court ultimately held that Sunshine could neither be expected to proceed under the original site plan nor be burdened with liability arising from NOIDA’s failure to provide the promised 45-metre road.
- It characterised NOIDA’s denial of Zero Period relief and its continuing refusal to sanction a revised site plan as βunreasonable and untenable in law.β
Supreme Court Dismisses NOIDAβs Appeals
- Finding no error in the Allahabad High Court’s judgment, the Supreme Court dismissed all three civil appeals filed by NOIDA and upheld the relief granted to Sunshine Trade Tower.
- The Court did not find it necessary to examine the developer’s additional pleas concerning discrimination or comparison with other similarly situated developers.
- The developer also gave a statement before the Supreme Court that the project would be completed within four years from approval of the revised site plan and that amounts due would be paid in eight instalments.
- The Supreme Court directed NOIDA to take note of this statement and issue necessary directions for commencement of the project with revised schedules. No order as to costs was passed.
Why the Judgment Matters
The ruling is significant for real-estate developers dealing with government development authorities. It establishes that policy benefits cannot necessarily be denied through an excessively literal interpretation when the very purpose of the policy would thereby be defeated.
More importantly, where a statutory authority promises infrastructure forming an essential component of an allotment and sanctioned development plan, it cannot ordinarily impose financial consequences upon the developer for delays materially attributable to the authority’s own failure.
The judgment also recognises the commercial reality that access and frontage are integral to the viability of a commercial real-estate project.
The existence of some physical means of reaching a plot is not necessarily equivalent to providing the effective and legitimate access contemplated by the allotment and sanctioned plan.
Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.
Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.
Source: Supreme Court
Handy Download:
Write to us at office@aadrikaalaw.com
Tel: +91-11-4999 2707

