Karnataka HC Clarifies RERA Jurisdiction Over Delayed-Possession Interest Claims

The Karnataka High Court has set aside a K-RERA order directing SMR Builders Pvt. Ltd. to pay βΉ15.68 lakh in delayed-period interest, holding that the authority denied the developer a meaningful opportunity to respond before deciding the complaint.
The dispute: delayed possession at SMR Vinay Estella
The case arose from a flat purchase in the SMR Vinay Estella residential project at Singapura Village, Yelahanka, Bengaluru. The purchaser and his wife entered into sale and construction agreements with SMR Builders on 10 May 2017 for Flat No. 412 in the E2 Block.
Under the agreement, possession was to be handed over within 24 months, plus a six-month grace period, making the relevant deadline 10 November 2019. The developer maintained that the project was completed within time and that other buyers in the same block began taking possession from 11 September 2019. It contended that the purchaser did not take possession at that stage, completed the sale deed on 26 June 2020, and was then placed in possession.
The purchaser later approached the Karnataka Real Estate Regulatory Authority (K-RERA), claiming delay-related relief. On 7 October 2023, K-RERA ordered the developer to pay βΉ15,68,344 as delayed-period interest up to 21 March 2022, along with interest calculated at MCLR + 2% for the period from 12 May 2019 to 21 March 2022.
SMR Builders challenged that order before the High Court.
Courtβs central finding: K-RERA did not follow natural justice
The High Court found a clear procedural failure in K-RERAβs handling of the complaint. The order sheet showed that, after the purchaser filed a calculation memo and supporting papers, the authority posted the matter for orders without giving the developer a proper chance to answer those materials or present its case.
The Court emphasized that giving parties an adequate opportunity to make their submissions is not a technicality. It is a foundational requirement in judicial and quasi-judicial proceedings.
Although an appeal was available under Section 44 of the Real Estate (Regulation and Development) Act, 2016, the Court held that the breach of natural justice justified the developerβs writ petition. The October 2023 order was therefore quashed and the matter sent back to K-RERA for a fresh decision.
Regulatory Authority can decide delayed-interest claims
A significant part of the case concerned the division of powers between K-RERA and an Adjudicating Officer under the RERA framework.
SMR Builders argued that the purchaserβs claim was essentially one for compensation and should have been decided only by an Adjudicating Officer, who must be or have been a District Judge. The developer relied on the Supreme Courtβs decision in New Tech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh.
The High Court rejected this jurisdictional objection. Drawing on the Supreme Courtβs interpretation, it distinguished between two categories of relief:
- K-RERA, as the Regulatory Authority, may decide claims for refund, interest on refunded amounts, interest for delayed delivery of possession, penalties, and related interest.
- An Adjudicating Officer has exclusive authority to determine compensation and interest on compensation under Sections 12, 14, 18 and 19 of the RERA Act.
Because the impugned order granted delayed-period interest, the Court held that K-RERA had jurisdiction to consider the complaint. In other words, the order failed because of the procedure used, not because the Regulatory Authority lacked authority over delayed-possession interest.
K-RERAβs complaint guidelines were upheld
The developer also challenged K-RERAβs undated complaint guidelines, arguing that they improperly displaced the Adjudicating Officerβs jurisdiction.
The Court declined to invalidate the guidelines. It found that they broadly explained complaint procedures, the remedies potentially available to homebuyers, the applicable interest framework, and the position for projects completed before or after 30 April 2017. The guidelines did not, in the Courtβs view, contradict the Supreme Court ruling in New Tech Promoters.
The judgment also recognized K-RERAβs authority under Section 31(2) of the RERA Act to prescribe the manner in which complaints are filed and processed.
Strong direction to follow Rule 29 procedures
The Courtβs most consequential institutional observation concerned K-RERAβs complaint process. It noted that the prescribed procedure for a summary inquiry under Rule 29(2) of the Karnataka RERA Rules, 2017, appeared not to have been followed in the present matter. The Court further observed that this concern extended beyond this individual dispute.
Accordingly, K-RERA was directed to strictly follow Rules 29 and 30 when adjudicating complaints. This requires a more structured process than merely relying on a complaint and a calculation memo. Parties must receive a fair opportunity to submit their materials and contest the opposing case before an order is made.
For developers, this reinforces the importance of preserving project-completion records, possession offers, correspondence, and proof of service. For homebuyers, it confirms that delayed-possession interest remains available through K-RERA, but the claim must be resolved through a procedurally fair inquiry.
Bench composition: technical objection rejected, administrative update required
SMR Builders also argued that the order was invalid because the member heading the relevant K-RERA bench was not the person named in an earlier notification constituting the benches.
The Court called this objection overly technical. It reasoned that personnel changes naturally occur when members retire, transfer, or complete their terms, and that a successor occupying the relevant office would not lose jurisdiction merely because an older notification named a predecessor.
However, the Court still directed K-RERA to issue corrigenda or amended notifications whenever the Chairperson or members change. It suggested that future notifications should preferably identify benches by designation rather than by individual names.
What the judgment means
The ruling clarifies that K-RERA can award interest for delayed possession, while claims seeking compensation as a distinct remedy fall within the Adjudicating Officerβs exclusive domain. More importantly, it makes clear that K-RERA must follow the procedural safeguards in the Karnataka RERA Rules before deciding complaints.
The case has been remitted to K-RERA for fresh consideration under Section 18 of the RERA Act and Rule 29(2) of the Karnataka RERA Rules, 2017. The eventual outcome on the purchaserβs delay-related claim will therefore depend on a new inquiry conducted with both sides given a proper opportunity to be heard.
Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.
Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.
Source: Karnataka High Court
Handy Download:
Write to us at office@aadrikaalaw.com
Tel: +91-11-4999 2707