Tag: #Facebook

  • Supreme Court: Conscious Possession Must Be Established for Conviction Under Section 15 of NDPS Act

    Supreme Court: Conscious Possession Must Be Established for Conviction Under Section 15 of NDPS Act

    Date: 17.10.2026

    The Supreme Court of India dismissed the State of Punjab’s appeal against the acquittal of Hari Singh and other accused, holding that a failure to question them on the central allegation of conscious possession under Section 313 of the Code of Criminal Procedure (CrPC) materially weakened the prosecution’s case.

    Case at a glance

    In State of Punjab v. Hari Singh & Ors., the respondents had initially been convicted under Section 15 of the Narcotic Drugs and Psychotropic Substances Act, 1985 (NDPS Act). The trial court sentenced each accused to 10 years’ rigorous imprisonment and imposed a fine of Rs. 1,00,000.

    The prosecution alleged that police officers found the accused sitting on 16 gunny bags of poppy husk, each weighing 30 kilograms, near sugarcane fields on 9 July 1999. The accused were arrested after the bags were searched in the presence of a Deputy Superintendent of Police, following their request for the presence of a Gazetted Officer.

    The Punjab and Haryana High Court later acquitted the accused. The State challenged that acquittal before the Supreme Court.

    The central legal issue: conscious possession

    Section 15 of the NDPS Act penalizes unlawful possession of poppy straw. The Court emphasized that possession in this context is not limited to physical custody. For criminal liability, the prosecution must establish conscious possession: possession coupled with awareness and the required mental element.

    The judgment explains that β€œpossession” can take different forms depending on the circumstances. It may be:

    • Physical possession, where a person directly holds or carries an article; or
    • Constructive possession, where a person has the power and control to deal with the article even if it is not physically on them.

    The Court noted that the evidence in this case, including the allegation that the accused were sitting on the bags, was relevant to conscious possession. Under Sections 35 and 54 of the NDPS Act, statutory presumptions may arise once possession is established. A person claiming that possession was not conscious may need to explain circumstances particularly within their knowledge.

    However, proving or relying on possession was not enough by itself. The accused had to be given a fair opportunity to respond to that allegation.

    Why the Section 313 CrPC examination was decisive

    The Supreme Court found that the accused were not asked any question during their examination under Section 313 CrPC about possession or conscious possession of the contraband.

    Section 313 requires the court, after the prosecution evidence closes, to question the accused so they can personally explain circumstances appearing against them. This is a core safeguard in a criminal trial, not a procedural formality.

    The Court reaffirmed several principles:

    • Every material incriminating circumstance should be put to the accused. This allows a meaningful explanation or defence.
    • A circumstance not put to the accused ordinarily cannot be used against them.
    • The purpose is fairness. The provision gives effect to the natural-justice principle that a person must have an opportunity to answer the case against them.
    • Prejudice matters. An omission does not automatically invalidate every trial, but a conviction cannot safely rest on a vital fact that the accused were never asked to explain.

    Here, conscious possession was the essence of the accusation under the NDPS Act. Because that crucial issue was omitted from the Section 313 examination, the omission was held to have a vital effect on the prosecution case.

    The Court’s guidance on personal appearance under Section 313

    The judgment also discussed when an accused must personally appear to answer Section 313 questions. The general rule is that the accused should be personally examined, particularly in cases more serious than summons cases.

    Still, the Court endorsed a limited practical exception for genuine hardship. If an accused already exempted from personal appearance cannot attend because of substantial expense, physical incapacity, or another justified difficulty, the court may permit written answers through a questionnaire.

    This alternative requires safeguards, including:

    1. A written application supported by the accused’s own affidavit explaining the difficulty.
    2. An assurance that the accused will not suffer prejudice from the arrangement.
    3. An undertaking not to challenge the exemption later.
    4. Personally authenticated answers, signed by the accused on every page and returned within the deadline fixed by the court.

    The Court stressed that this is an exceptional arrangement. It cannot become a way for counsel to substitute their own answers for the accused’s statement.

    Outcome of the appeal

    The Supreme Court upheld the High Court’s acquittal and dismissed the State of Punjab’s appeal. It concluded that, despite evidence bearing on conscious possession, the failure to put that essential allegation to the accused under Section 313 CrPC justified refusing to interfere with the acquittal.

    The Court did remove one part of the High Court’s order: directions to initiate action against certain officials were expunged because such directions should not have been issued while deciding the criminal appeal.

    Key takeaway

    This decision shows that even in serious NDPS prosecutions, procedural fairness remains indispensable: a conviction cannot rely on a decisive incriminating circumstance, such as conscious possession, unless the accused has been given a proper opportunity to explain it under Section 313 CrPC.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • Delhi HC: ROC Approval Does Not Validate a Corporate Name That Violates Companies Act

    Delhi HC: ROC Approval Does Not Validate a Corporate Name That Violates Companies Act

    Date: 17.10.2026

    The Delhi High Court directed Mondelez India Private Limited to adopt a different corporate name after finding that its use of β€œMondelez” was deceptively similar to the pre-existing name of Mondelez Foods Private Limited.

    Background of the dispute

    Mondelez Foods Private Limited, incorporated on 28 May 2012, challenged the Registrar of Companies’ approval of a name change by Nonstop Logistics India Private Limited to β€œMondelez India Private Limited.” The new certificate of incorporation was issued on 11 September 2012.

    The petitioner argued that β€œMondelez” was a distinctive and coined term associated with the Mondelez group and its trademark rights. It stated that it was authorized to use the name and that the later adoption by the other company was intended to exploit the established reputation connected with the word.

    Documents submitted for the name-change request recorded that the company sought the new name because its directors considered it β€œlucky for business transactions.” The petitioner also noted that the company applied to register a β€œMondelez” logo for similar goods.

    Earlier action and rejection by the Regional Director

    Before approaching the High Court, Mondelez Foods Private Limited sent legal notices and filed a rectification representation under Section 22 of the Companies Act, 1956. The Regional Director rejected the representation on two principal grounds:

    • The petitioner was not itself the registered proprietor of the β€œMondelez” trademark.
    • More than 12 months had passed since the registration of the changed corporate name.

    Separately, Intercontinental Great Brands, LLC, formerly known as Kraft Foods Global Brands, LLC, and Mondelez Foods Private Limited obtained a decree in a civil suit on 24 July 2014. That decree restrained the company and related defendants from using β€œMondelez” as a trademark, trade name, corporate name, or part of a corporate name.

    Court’s findings

    Justice Vibhu Bakhru observed that the respondent company did not appear to contest the petition. As a result, the petitioner’s allegations about the respondent’s conduct and intent remained uncontroverted.

    The Court held that the adoption of β€œMondelez” was dishonest and mala fide. It emphasized that β€œMondelez” is a coined and distinctive word, as well as a prominent part of both companies’ names. The Court therefore found the names deceptively similar.

    Under Section 20 of the Companies Act, 1956, a company cannot be registered under an undesirable name. A name may be considered undesirable if it is identical with or too nearly resembles the name of an existing company or a registered trademark. The Court found that the respondent’s name fell within this prohibition and should not have been registered by the Registrar of Companies.

    Effect of the Companies Act, 2013

    The Court noted uncertainty in the wording of Section 22 of the 1956 Act, particularly concerning the 12-month period for a direction to change a company name. However, it considered the newer Companies Act, 2013, which empowers the Central Government to direct a company to change a name that is identical with or too nearly resembles a previously registered company name.

    Because β€œMondelez India Private Limited” too closely resembled β€œMondelez Foods Private Limited,” the Court concluded that the Regional Director had the authority to require a correction.

    Final order

    On 7 July 2017, the Delhi High Court directed the Regional Director to issue the necessary instructions requiring Mondelez India Private Limited to change its name. The replacement name must not be identical with or resemble the petitioner’s name or that of any other existing company.

    The company and its directors were also expressly directed to ensure compliance with the name-change requirement.

    Why the ruling matters

    The decision reinforces that company-name registration is not a mere administrative formality. A distinctive pre-existing corporate identity can be protected where a later name is confusingly similar, particularly when the record indicates dishonest adoption. It also illustrates the interaction between company-name law and trademark protection in preventing misleading corporate identities.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • Bombay HC: Builders Cannot Collect More Than 10% of Flat Price Without Registered Sale Agreement β€” RERA Section 13 Compliance Mandatory

    Bombay HC: Builders Cannot Collect More Than 10% of Flat Price Without Registered Sale Agreement β€” RERA Section 13 Compliance Mandatory

    Date: 17.10.2026

    The Bombay High Court has directed Rare Townships Pvt. Ltd. to execute and register a RERA-compliant agreement for sale within four weeks, while treating 4 October 2024 as a tentative possession date pending final determination by the Maharashtra Real Estate Appellate Tribunal.

    Background of the dispute

    The dispute concerns a residential flat in the developer’s Ghatkopar project, originally marketed as β€œRising City” and later registered under RERA as β€œNorth Sea Heights (A-1).”

    The buyers initially received a holding receipt in January 2011 for a different flat. The parties subsequently changed the unit, and a provisional allotment letter dated 30 November 2014 was issued for Flat No. 805 in Building A-1, with a stated consideration of Rs. 1.248 crore.

    The parties ultimately agreed that the buyers had paid Rs. 38.47 lakh by 2016. Despite this payment, no registered agreement for sale was executed. The core disagreements included the unpaid balance, the agreement’s terms, the possession timeline, parking and amenities, and each side’s liability for delay.

    RERA authority’s earlier directions

    In July 2025, MahaRERA partly allowed the buyers’ complaint. It required the developer to execute a registered agreement for sale under Section 13 of the Real Estate (Regulation and Development) Act, 2016, based on the allotment letter.

    MahaRERA also held that:

    • The buyers would pay the outstanding consideration and any applicable interest for delayed payments under the statutory framework.
    • The developer would pay interest for delayed possession from 4 October 2024 until it offered possession with an Occupation Certificate.
    • The parties’ respective payment obligations could be adjusted and set off when possession was delivered.

    The buyers appealed for a more complete RERA-compliant agreement, including parking, amenities, model-agreement protections and safeguards against payment demands or termination before registration.

    Interim tribunal order and developer’s challenge

    The Appellate Tribunal initially directed the developer to provide and execute a RERA-compliant agreement. It also restrained the developer from demanding further money or issuing termination notices until the agreement was executed and registered. A review order corrected the buyers’ payment figure to Rs. 38.47 lakh and corrected the allotment-letter date.

    Rare Townships challenged the interim order in the High Court. Its principal objection was that the Tribunal had effectively decided disputed issues at an interim stage, particularly by requiring the agreement to state a possession date and by excluding interest for alleged payment delays before the agreement’s execution.

    High Court’s reasoning

    The Court emphasized that a registered agreement for sale is not optional once substantial sums have been accepted from a buyer. It noted that both the earlier Maharashtra Ownership Flats Act framework and RERA seek to prevent promoters from accepting significant advances without documenting the parties’ rights and obligations in a registered agreement.

    Under Section 13 of RERA, a promoter cannot accept more than 10% of an apartment’s cost before entering into a registered written agreement for sale. The agreement must cover key matters, including project specifications, payment schedules, the possession date and default interest.

    Here, the Court found that the developer had accepted more than 30% of the agreed consideration without executing the agreement. It therefore upheld the essential requirement to execute a registered, RERA-compliant agreement.

    The Court drew a distinction, however, between requiring an agreement and conclusively determining the contractual possession date. The possession date remained an issue in the buyers’ pending appeal before the Appellate Tribunal. The High Court therefore modified the interim arrangement rather than treating that issue as finally settled.

    Final directions

    The Court disposed of the second appeal with these principal directions:

    • Tentative possession date: The agreement must record 4 October 2024 as the possession date.
    • No final determination: That date is tentative, without prejudice to either side, and remains subject to final adjudication by the Appellate Tribunal.
    • Rectification if required: If the Tribunal changes the possession date, the parties’ rights and liabilities will follow that determination and they must execute a deed of rectification.
    • RERA-compliant agreement: The agreement must comply with Section 13 of RERA and the prescribed model agreement under Maharashtra’s 2017 RERA Rules.
    • Time limit: The developer must execute and register the agreement within four weeks of the judgment.
    • Issues kept open: All remaining disputes, including payment, interest, parking, amenities, compensation and the final possession timeline, remain open before the Appellate Tribunal.

    Why the decision matters

    The ruling reinforces that developers cannot retain substantial buyer payments while postponing the registered agreement for sale. It also confirms that a RERA-compliant agreement must transparently state essential commercial terms, including payment obligations, possession and default consequences.

    At the same time, the judgment preserves procedural fairness: an interim order can secure the statutory agreement and protect buyers from premature demands or termination, but contested issues such as the final possession date must remain available for full appellate adjudication.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Bombay High Court Holds That Non-Recovery of a Journey Ticket Does Not Defeat Railway Accident Compensation Claim

    Bombay High Court Holds That Non-Recovery of a Journey Ticket Does Not Defeat Railway Accident Compensation Claim

    Date: 17.10.2026

    The Bombay High Court has awarded β‚Ή8,00,438.36 to the parents of a man who died after falling from a crowded local train, holding that the absence of a ticket for one leg of his journey did not by itself disprove that he was a bona fide passenger.

    Background of the case

    Bhaskar Kandh Panda and Prafulla, also known as Pranita Bhaskar Panda, sought compensation following the death of their son, Sandeep P. Panda, on 1 September 2015. According to their case, Sandeep travelled from Kurla to Belapur for personal work and later boarded a local train from Belapur toward Chhatrapati Shivaji Maharaj Terminus (CSMT) to meet a friend.

    The parents said that the train was heavily crowded and that Sandeep, who was standing near the door, was pushed and fell between Kurla and Chunabhatti stations. He suffered severe head injuries and later died at Sion Hospital.

    A railway ticket for the Kurla-to-Belapur journey was recovered from his wallet during the inquest. However, the ticket for the later Belapur-to-CSMT journey was not found.

    Why the Railway Claims Tribunal rejected the claim

    The Railway Claims Tribunal initially dismissed the parents’ compensation application in March 2020. Although it accepted that Sandeep had fallen from a train and died in an untoward incident, it concluded that he was not a bona fide passenger because the ticket for the Belapur-to-CSMT leg was missing.

    Central Railway defended that conclusion, arguing that the deceased’s account of travel was unreliable and that standing near a train door amounted to negligence. It also contended that there was no eyewitness to establish the alleged fall.

    High Court’s findings

    Justice Aarti Sathe found the Tribunal’s reasoning internally inconsistent. The Tribunal had already accepted the police material, inquest panchanama and railway records showing that Sandeep fell from a train between Kurla and Chunabhatti and died from the resulting injuries. It could not, the High Court held, deny compensation solely because one ticket was not recovered.

    The Court relied on the Supreme Court’s ruling in Union of India v. Rina Devi, which clarifies that a missing ticket does not automatically defeat a railway accident claim. A claimant may meet the initial burden by filing an affidavit setting out relevant facts, after which the burden shifts to the Railways to rebut the case through the surrounding evidence.

    In this case, the parents had produced an affidavit and supporting records, while a valid one-way ticket was recovered from the deceased. The Railways did not produce sufficient evidence to establish that the death fell within any statutory exception under Section 124A of the Railways Act, 1989.

    Key legal principles reaffirmed

    • A missing ticket is not conclusive: The absence of a ticket after a fatal railway accident cannot, by itself, establish that the deceased was travelling without authority.
    • Evidence must be assessed as a whole: The Court considered the recovered ticket, inquest record, police report, affidavit and finding that the death resulted from a train fall.
    • Negligence does not automatically bar compensation: The Railways did not prove that the case fell under an exception to statutory liability merely because the deceased was allegedly near the door of a crowded train.
    • Beneficial legislation requires a liberal approach: The Railways Act’s compensation provisions are intended to protect victims and dependants. Where two reasonable interpretations are possible, the one favouring the beneficiary should be preferred.

    Compensation awarded

    The High Court set aside the Tribunal’s dismissal and allowed the claim. It noted that compensation for death under the applicable rules had increased from β‚Ή4 lakh to β‚Ή8 lakh after the 2016 amendment.

    Applying the principle that claimants should receive the higher of the applicable amounts, the Court awarded β‚Ή8,00,438.36. This amount reflects the original β‚Ή4 lakh compensation with interest at 9% per year from the accident date, which marginally exceeded the revised fixed compensation of β‚Ή8 lakh.

    The award is to be divided equally between the deceased’s father and mother. Central Railway must deposit the amount within eight weeks after receiving their bank details; any delay will attract further interest at 9% per annum.

    Significance of the ruling

    The decision reinforces that railway compensation claims cannot be rejected on technical grounds when the overall evidence supports an untoward railway incident. It also underscores the Railway Administration’s obligation to rebut a credible claim rather than relying only on the non-recovery of a ticket after an accident.

    For families pursuing compensation after railway accidents, the judgment highlights the importance of preserving available documents, filing a clear affidavit describing the journey and accident, and relying on inquest, police and railway records to establish the circumstances of the incident.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Karnataka High Court Quashes ITP Act Proceedings

    Karnataka High Court Quashes ITP Act Proceedings

    Date: 17.10.2026

    The Karnataka High Court has quashed two criminal cases against Maxim K. Kurian after the State failed to show that the officers who conducted the raids were legally appointed as Special Police Officers under the Immoral Traffic (Prevention) Act, 1956.

    The order, delivered by Justice H.P. Sandesh on 15 October 2026, disposed of Criminal Petition Nos. 5994 of 2019 and 272 of 2020. The cases arose from separate police cases in Mangaluru but involved the same legal issue: whether the investigating officers had the statutory authority required to investigate offences under the ITP Act.

    The two cases

    In the first petition, Kurian, identified as accused No. 5, sought to quash proceedings in C.C. No. 3260/2017. The case stemmed from Crime No. 8/2017 registered at Barke Police Station and alleged offences under Sections 3(1), 4, 5 and 8 of the ITP Act.

    The second petition concerned C.C. No. 2311/2019, arising from Crime No. 73/2017 registered at Mangaluru East Police Station. In that case, Kurian was accused No. 1 and faced allegations under Sections 4 and 5 of the Act.

    Although the cases originated at different police stations, the Court heard them together because both turned on the same legal question concerning the authority of the officers involved.

    Central legal issue: appointment of Special Police Officers

    Kurian argued that the raids and investigations did not comply with Sections 13 and 15 of the ITP Act. Section 13 provides for the appointment of Special Police Officers to deal with offences under the statute, while Section 15 regulates searches conducted in connection with such offences.

    The petitioner’s counsel contended that:

    • No government notification was produced showing that the investigating officers had been appointed as Special Police Officers under the Act.
    • The officers therefore lacked the specific statutory authority needed to conduct raids and investigate the alleged offences.
    • No search warrant had been obtained before the raids.
    • Even where a warrantless search may be permitted, it must be carried out by an authorized Special Police Officer and the legal safeguards must be followed.

    The State submitted that the officer who conducted the raid held the rank of Inspector of Police. However, it did not rely on or produce a notification showing that the officer had been specially appointed by the State to deal with offences under the ITP Act.

    Why the Court quashed the proceedings

    The Court found that the State had not established that the investigating officer was an authorized Special Police Officer. Justice Sandesh noted that earlier Karnataka High Court decisions had treated compliance with the relevant ITP Act provisions as mandatory.

    The Court relied on the principle from previous rulings that, where there is no notification demonstrating that an investigating officer qualifies as a Special Police Officer under the Act, the investigation cannot be sustained in law.

    The decision underscores that an officer’s general police rank alone does not establish the special authorization required for investigations under a statute with its own procedural framework. For ITP Act cases, the State must be able to show the officer’s appointment under the Act when that authority is challenged.

    The ruling

    The High Court allowed both petitions and quashed the proceedings against Kurian in:

    • C.C. No. 3260/2017, arising from Barke Police Station Crime No. 8/2017; and
    • C.C. No. 2311/2019, arising from Mangaluru East Police Station Crime No. 73/2017.

    Broader significance

    The ruling reinforces the importance of procedural compliance in criminal investigations under special laws. It confirms that, in ITP Act prosecutions, the State must demonstrate that the officer conducting the raid or investigation was validly appointed under the statutory scheme.

    Where that foundational requirement is not met, proceedings may be vulnerable to being quashed. The decision is based on the procedural validity of the investigations and does not determine the underlying factual allegations on their merits.

    Listen to this on our #YouTube Channel

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Rajasthan HC Grants Bail Where Samples Were Drawn from Just One of Five Bags

    Rajasthan HC Grants Bail Where Samples Were Drawn from Just One of Five Bags

    Date: 26.09.2026

    The Rajasthan High Court has granted bail to an accused in an NDPS case involving an alleged recovery of 79.400 kg of Doda Chura (poppy straw), after finding that samples for forensic examination were taken from only one out of five bags allegedly recovered from him.

    Justice Ganesh Ram Meena held that since no samples were drawn from the remaining four bags, only the material contained in the sampled bag could, at this stage, be treated as the alleged contraband. That bag weighed 19.80 kg, which was below the commercial quantity threshold. Consequently, the stringent restrictions governing bail under Section 37 of the Narcotic Drugs and Psychotropic Substances Act, 1985 were not attracted in the circumstances considered by the Court.

    Case Arose From Alleged Recovery of 79.400 Kg Doda Chura

    • Sitaram alias Udham Meena filed his second bail application under Section 483 of the Bharatiya Nagarik Suraksha Sanhita, 2023 (BNSS).
    • The proceedings arose from FIR No. 94/2025, registered at Police Station Harnavda Shahji, District Baran, Rajasthan, for offences under Sections 8, 15 and 25 of the NDPS Act.
    • The petitioner’s first bail application had earlier been dismissed as withdrawn by the High Court on 8 May 2026.
    • According to the FIR, the alleged contrabandβ€”Doda Churaβ€”was recovered from the petitioner’s possession in five separate bags, having a combined weight of 79.400 kg.

    Samples Drawn From Only Bag β€˜C’

    • The petitioner’s principal argument concerned the manner in which the samples were drawn.
    • According to the inventory report prepared before the Judicial Officer, two samples were taken only from the packet/bag marked β€˜C’. No samples were taken from the remaining four bags for examination by the Forensic Science Laboratory (FSL).
    • The defence therefore argued that there was no forensic material to establish that the substances contained in bags A, B, D and E were also contraband.
    • It was submitted that only the contents of bag C could be treated as alleged contraband for the purpose of considering bail.
    • Crucially, bag C weighed only 19.80 kg. The petitioner argued that this was below commercial quantity and hence the restrictions contained in Section 37 of the NDPS Act would not apply.

    State: All Five Bags Contained Similar Material

    • The Public Prosecutor opposed the second bail application.
    • The State argued that samples were taken from only one bag because the material found in the other bags appeared to be the same or similar.
    • It further contended that the total alleged recovery was above commercial quantity and therefore the restrictions under Section 37 of the NDPS Act continued to apply.
    • The High Court, however, did not accept that contention for the purpose of deciding the bail application.

    Court Examines Inventory and Judicial Officer’s Certificate

    • The High Court examined the record and found that the alleged recovery made on 31 May 2025 had been packed in five separate bags marked A, B, C, D and E.
    • The inventory report and certificate issued by the Additional Chief Judicial Magistrate No. 2, Chhabra, Baran on 6 June 2025 showed that only two samples, marked F and G, were drawn from bag C.
    • No sample was drawn from bags A, B, D or E.
    • This factual circumstance became decisive for the bail determination.

    Unsampled Bags Could Not Be Treated as Contraband at Bail Stage

    • The High Court held that in the absence of samples from the other four bags, the material contained in bag C alone could be treated as the alleged contraband for the purpose under consideration.

    The Court recorded:

    • β€œthe material which has been found to be in bag marked as-C can only be treated to be alleged contraband”
    • Since bag C weighed 19.80 kg, the quantity attributable to the sampled material was below commercial quantity.
    • The ruling is significant because the total physical recovery alleged by the prosecution was 79.400 kg. However, for the bail assessment, the Court did not aggregate the contents of the four bags from which no sample had been taken with the sampled bag merely because the substances appeared similar.

    Rajasthan HC Relies on Hariram v. State of Rajasthan

    • The petitioner relied upon the Rajasthan High Court’s recent order in Hariram v. State of Rajasthan, S.B. Criminal Miscellaneous Bail Application No. 741/2026, decided on 20 April 2026.
    • In Hariram, six bags were allegedly recovered containing Doda Chura. However, samples had been drawn from only two bagsβ€”marked A and E.
    • The combined weight of those two sampled bags was 45.400 kg, below the commercial quantity of 50 kg applicable to poppy straw.
    • The Court in Hariram observed that because no samples had been taken or sent to the FSL from the remaining bags, those bags could not be treated as containing contraband merely on assumption, particularly when there was nothing on record showing that the entire recovered material had first been mixed and thereafter sampled.
    • The same reasoning was applied in Sitaram’s case.

    Supreme Court’s Puranmal Jat Decision Considered

    The Hariram order, reproduced in the present judgment, also relied upon the Supreme Court’s decision in:

    • Puranmal Jat v. State of Rajasthan, Criminal Appeal No. 3394/2023 arising out of SLP (Crl.) No. 10670/2023, decided on 2 November 2023.
    • In that case, the alleged recovery was approximately 35 kg and 150 grams of Doda Posh/poppy straw, while the commercial quantity was 50 kg.
    • The Supreme Court observed that because the recovered quantity was below commercial quantity, the restriction on grant of bail under Section 37 of the NDPS Act did not apply. The accused had also remained in custody for more than seven months and the charge sheet had already been filed.

    Section 37 NDPS Act Not Attracted to 19.80 Kg Sampled Bag

    • Applying the above reasoning, the Rajasthan High Court treated 19.80 kg in bag C as the relevant alleged contraband quantity for the bail consideration.
    • Because this was below commercial quantity, the defence contention was that the special restrictions under Section 37 were not attracted, and the Court’s reasoning proceeded on that basis.
    • This distinction was particularly important because Section 37 imposes stringent conditions for release on bail in cases involving commercial quantity.
    • The order, however, is a bail-stage determination and does not finally adjudicate the nature or quantity of the entire seized material.

    More Than One Year in Custody

    • The Court also took into consideration the period of incarceration.
    • Sitaram had remained in custody since 31 May 2025, meaning that by the date of the order on 25 September 2026, he had spent more than one year in custody.
    • Considering the sampling issue, the quantity of the sampled bag and the period of custody, the High Court found it just and proper to enlarge him on bail.
    • Importantly, the Court expressly stated that it was doing so without expressing any opinion on the merits or demerits of the case.

    Second Bail Application Allowed

    • The Rajasthan High Court accordingly allowed the second bail application.

    The Court directed Sitaram alias Udham Meena to be released upon furnishing:

    • a personal bond of β‚Ή1,00,000; and
    • two sureties of β‚Ή50,000 each,

    to the satisfaction of the Trial Court.

    He was also directed to remain present before the Trial Court, or any court to which the proceedings may be transferred, on subsequent hearing dates and whenever required.

    Bail Can Be Cancelled for Similar Future Offence

    • The High Court imposed an additional safeguard.
    • It directed that if the petitioner is found involved in any other criminal case of a similar nature in the future, the prosecution would be at liberty to move an application seeking cancellation of his bail. Sitaram Alias Udham Meena RHC
    • Thus, the order grants liberty to the accused pending trial but leaves the prosecution free to seek cancellation if the stipulated condition is breached.

    Cases Referred

    Two decisions were central to the reasoning recorded in the order:

    1. Hariram v. State of Rajasthan, S.B. Criminal Miscellaneous Bail Application No. 741/2026, decided on 20 April 2026 β€” relied upon for the principle that where multiple bags are separately seized but only some are sampled, unsampled bags cannot automatically be treated as contraband in the absence of FSL examination or evidence that the entire material was mixed before sampling.
    2. Puranmal Jat v. State of Rajasthan, Criminal Appeal No. 3394/2023 arising from SLP (Crl.) No. 10670/2023, decided on 2 November 2023 β€” Supreme Court decision noting that where recovered poppy straw was below the stipulated commercial quantity, the Section 37 restriction did not apply.

    Key Takeaway

    The ruling underscores the importance of representative sampling and forensic examination in multi-bag NDPS recoveries, particularly when the prosecution seeks to rely upon the combined weight to invoke the stringent commercial-quantity bail restrictions under Section 37.

    Where five separate bags were allegedly recovered but the inventory showed that samples were taken from only one bag, the Rajasthan High Court treated only the 19.80 kg contained in that sampled bag as the alleged contraband for the purpose of deciding bail. Since that quantity was below commercial quantity and the accused had spent more than a year in custody, the Court granted bail.

    The ruling should nevertheless be read in its procedural context: the High Court did not acquit the accused or finally hold that the remaining four bags contained no contraband.

    Its determination was confined to the second bail application, and the Court expressly refrained from expressing any opinion on the merits of the prosecution case.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • CESTAT Mumbai Allows Customs Duty Exemption on Dowtherm Heat Transfer Fluid Under SHIS Scheme

    CESTAT Mumbai Allows Customs Duty Exemption on Dowtherm Heat Transfer Fluid Under SHIS Scheme

    Date: 26.09.2026

    The Customs, Excise & Service Tax Appellate Tribunal (CESTAT), Mumbai has held that Dowtherm RP Heat Transfer Fluid/Dowtherm A Heat Transfer Fluid, used for the initial charging and continuous operation of a Continuous Polycondensation (CP) Plant for manufacturing polyester products, falls within the definition of β€œcapital goods” and is consequently eligible for Customs duty exemption under Notification No. 104/2009-Customs dated 14 September 2009.

    Setting aside the Commissioner’s order, the Tribunal held that the thermic fluids fulfilled the statutory requirements of the Status Holders Incentive Scrip (SHIS) Scheme under the Foreign Trade Policy and that Customs was not justified in denying the exemption merely because the goods were chemicals falling under Chapter 29 or were described as inputs under SION.

    Background of the Dispute

    • Wellknown Polyesters Limited was engaged in manufacturing Polyester Filament Yarn (PFY), Polyester Oriented Yarn (POY), Fully Drawn Yarn (FDY), Draw Textured Yarn (DTY) and polyester chips at its Daman manufacturing facility.
    • For its manufacturing operations, the company had imported a Continuous Polycondensation Plant from Oerlikon Barmag under an EPCG authorisation during April–July 2012. The plant was imported without thermic fluid.
    • Subsequently, the company imported 3,01,296 kg of Dowtherm RP Heat Transfer Fluid/Dowtherm A Heat Transfer Fluid, valued at approximately β‚Ή9.86 crore, through Bills of Entry filed in October 2012. Customs duty involved was approximately β‚Ή2.55 crore.
    • Instead of paying the duty in cash, Wellknown Polyesters utilised eight SHIS scrips issued by the DGFT under the Status Holders Incentive Scrip Scheme and claimed exemption under Notification No. 104/2009-Customs. The goods were initially cleared by Customs extending the exemption.

    DRI Objects to SHIS Benefit

    • The Directorate of Revenue Intelligence (DRI), Ahmedabad Zonal Unit subsequently initiated an investigation on the ground that Notification No. 104/2009-Customs permitted duty-free import of capital goods, whereas Dowtherm heat-transfer fluid was, according to the Department, not capital goods.
    • DRI also relied upon the Standard Input Output Norms (SION), under which Dowtherm/Therminol and heat-transfer oil were identified as permitted inputs for manufacture of Polyester Partially Oriented Yarn and Polyester Filament Yarn. The Department therefore treated the material as an input rather than capital goods.
    • A Show Cause Notice dated 14 May 2013 consequently demanded approximately β‚Ή2.55 crore Customs duty with interest under Section 28(1) of the Customs Act, 1962, besides proposing confiscation under Section 111(o) and penalty under Section 112(a).
    • The Commissioner confirmed the duty demand and interest but refrained from confiscating the goods because they were no longer physically available and did not impose the proposed penalty. Wellknown Polyesters challenged that order before CESTAT.

    Appellant: Thermic Fluid Was Integral to Continuous Polycondensation Plant

    • The appellant argued that although the CP Plant and thermic fluid had been imported separately, both were required to operate together.
    • The thermic fluid was charged into the heaters, piping and vessels and thereafter continuously circulated in a closed loop between the heaters and reactors. The polyester polycondensation process required temperatures of approximately 270Β°C–300Β°C under high vacuum, making the thermic fluid critical for providing precise high-temperature heat while maintaining low system pressure.
    • The appellant relied upon the definition of β€œcapital goods” under the Foreign Trade Policy and Notification No. 104/2009-Customs, arguing that it was broad enough to cover goods required directly or indirectly for manufacture, including items necessary for the initial setting up and functioning of plant and machinery.
    • It also relied upon CBEC’s earlier clarification concerning transformer oil, under which oil required for filling/topping up a transformer was considered part of the equipment because the transformer could not function without it.

    Revenue: Chemical Falling Under Chapter 29 Cannot Be Capital Goods

    • The Department maintained that the imported thermic fluid was a chemical classifiable under Chapter 29 and therefore could not be regarded as plant, machinery, equipment or an accessory.
    • The Commissioner’s reasoning was that even though the chemical was indirectly used in manufacturing, its nature did not change into that of plant, machinery, equipment or accessories. The Department also relied upon the fact that SION treated Dowtherm as an input/raw material for polyester production.
    • CESTAT was therefore required to decide whether denial of the exemption under Notification No. 104/2009-Customs for the October 2012 imports was legally sustainable.

    CESTAT Examines SHIS Scheme and Definition of β€˜Capital Goods’

    • The Tribunal examined the Foreign Trade Policy 2009–2014 and observed that the objective of the SHIS Scheme was to promote investment in technology upgradation.
    • Paragraph 3.17.5 of the FTP permitted Duty Credit Scrips to be used for import of inputs or goods, including capital goods, subject to the stipulated conditions. More importantly, the FTP defined β€œcapital goods” broadly as plant, machinery, equipment or accessories required directly or indirectly for manufacture or production, including specified items such as refractories for initial lining and catalysts for initial charge.
    • Notification No. 104/2009-Customs, issued under Section 25(1) of the Customs Act, 1962, similarly exempted capital goods and specified components/spares/parts imported against SHIS Duty Credit Scrips from Customs duties, subject to its conditions.
    • CESTAT found the definition of β€œcapital goods” under the Customs notification and the FTP to be substantially identical.

    Thermic Fluid Critical to Functioning of CP Plant

    • The Tribunal accepted the technical evidence concerning the role played by Dowtherm in the Continuous Polycondensation Plant.
    • It observed that the thermic fluid enabled the plant to provide precise high-temperature heat while maintaining low pressure, thereby permitting efficient continuous polycondensation and energy-efficient manufacture of high molecular weight polyester.
    • On that basis, CESTAT concluded that the imported goods fulfilled the statutory requirements of the SHIS Scheme.
    • A particularly important factual finding arose from the Chartered Engineer’s Certificate. Out of the total 3,01,296 kg of imported thermic fluid, 2,92,920 kgβ€”approximately 97.2%β€”was used as a one-time/initial charge in the CP Plant’s Electric Thermal Oil Heater Boiler.
    • The fluid thereafter enabled continuous high-temperature operation at very low pressure for the polycondensation process.
    • The technical diagrams reproduced on pages 13–15 of the order further illustrate the closed-loop recirculation of Dowtherm between the thermic-fluid heater and CP Plant, the stages of polyester manufacture where heat transfer is required, and the Electric Thermal Oil Heater Boiler arrangement.

    Capitalisation in Books Also Supported Appellant

    • CESTAT additionally noted that the imported thermic fluid had been capitalised in Wellknown Polyesters’ books of account, as certified by its Chartered Accountants on 29 May 2026.
    • The Tribunal regarded this financial treatment as further evidence supporting the appellant’s case that the imported goods were treated as capital goods.

    Accordingly, the Bench held:

    • β€œthe impugned goods are covered under the definition of β€˜capital goods’”
    • and were therefore eligible for exemption under Notification No. 104/2009-Customs.

    CESTAT Relies on Reliance Communications Infrastructure

    • The Tribunal found support in Reliance Communications Infrastructure v. Commissioner of Customs, 2009 (240) E.L.T. 461 (Tri.-Bang.).
    • In that case, a Gas Suppression System included HFC 227 EA gas. The Tribunal had held that Customs could not dissect an integrated system and treat the gas required for its functioning as a mere consumable when the EPCG licence covered the complete system.
    • CESTAT applied the same reasoning to the thermic fluid, observing that where a material is essential to the functioning of the plant, its character cannot be determined merely by isolating it from the system in which it operates.

    Transformer Oil Analogy Applied to Dowtherm

    • CESTAT also referred to CBEC Circular No. 344/60/97-CX dated 22 October 1997, concerning transformer oil.
    • The circular recognised that a transformer cannot function without transformer oil and that the equipment cannot be regarded as complete without the oil filled into it.
    • Applying the same analogy, CESTAT held that if the Continuous Polycondensation Plant cannot function without thermic fluid, the fluid has to be treated as part of the plant, notwithstanding the absence of a specific Customs clarification concerning thermic fluid.

    Cases Cited by Wellknown Polyesters

    The appellant relied upon several judicial authorities in support of its interpretation of capital goods:

    S. No.CaseCitation
    1Reliance Communications Infrastructure v. Commissioner of Customs2009 (240) E.L.T. 461 (Tri.-Bang.)
    2Commissioner of Central Excise, Coimbatore v. Jawahar Mills2001 (132) E.L.T. 3 (S.C.)
    3Bharti Airtel Limited v. Commissioner of Central Excise, Pune2025 (391) E.L.T. 3 (S.C.)
    4Chief Commissioner of Central Goods and Service Tax & Ors. v. Safari Retreats Private Limited & Ors.2024 SCC OnLine SC 2691
    5Scientific Engineering House (P) Ltd. v. Commissioner of Income Tax, Andhra Pradesh(1986) 1 SCC 11
    • These authorities are expressly recorded in the appellant’s submissions.
    • Of these, the final reasoning expressly discusses and applies Reliance Communications Infrastructure.

    Final Decision: Wellknown Polyesters Wins Appeal

    CESTAT concluded that the Commissioner’s order denying the benefit of Notification No. 104/2009-Customs dated 14 September 2009 by refusing to treat Dowtherm RP/Dowtherm A Heat Transfer Fluid as capital goods β€œdoes not stand the scrutiny of law.”

    The Tribunal consequently set aside the Order-in-Original dated 7 October 2016 and allowed Wellknown Polyesters’ appeal in its favour.

    The ruling is significant for the interpretation of capital goods under export-promotion schemes, particularly where a material may chemically resemble an input or consumable but is technically required as an initial charge and thereafter continuously circulates as an integral part of plant operation.

    It also demonstrates that classification of an item as a chemical under Chapter 29, or its description as an β€œinput” under SION for a different regulatory purpose, is not by itself determinative of whether it can qualify as capital goods under the specific language and objective of an exemption notification.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

    Ravi Shekhar Jha – Advocate, Bar Council of Delhi

  • Punjab & Haryana HC: Development Authority Is a β€˜Promoter’ Under RERA and Liable for Delayed Possession

    Punjab & Haryana HC: Development Authority Is a β€˜Promoter’ Under RERA and Liable for Delayed Possession

    Date: 26.09.2026


    The Punjab and Haryana High Court has held that a Development Authority falls within the definition of β€œpromoter” under the Real Estate (Regulation and Development) Act, 2016 (RERA) and cannot escape the statutory consequences of delayed possession merely because a commercial site was auctioned on an β€œas is where is” basis or because the allotment terms contained a deemed-possession clause.

    Dismissing two appeals filed by the Bathinda Development Authority, Justice Harkesh Manuja upheld the order of the Real Estate Appellate Tribunal, Punjab granting interest under Section 18 of the RERA Act to allottee Leela Gupta for delayed possession of two SCO sites.

    Background: SCO Sites Purchased Through Auction and Transfer

    • The dispute concerned two SCO sites situated at Civil Lines, Power House Road, Bathinda.
    • Leela Gupta purchased SCO Site No. 1 through an open auction conducted by the Bathinda Development Authority on 5 August 2015. An allotment letter was issued on 1 December 2015 after payment of 20% of the principal amount along with 2% cancer cess.
    • Under the allotment letter, possession was required to be delivered within 90 days.
    • SCO Site No. 2 was not originally allotted to Gupta. She subsequently acquired it by transfer from the original allottees on 4 August 2017. Her grievance was that despite payment according to schedule, possession of the sites was not handed over in time because the necessary development work had not been completed.

    Earlier Proceedings Before PUDA and RERA

    • Gupta initially sought relief from the Estate Officer, Bathinda, contending that interest should not be charged for the period during which the sites were not ready for possession.
    • After her representation was rejected, she approached the High Court through CWP No. 24881 of 2018. The High Court permitted her to submit an appeal-cum-representation to the Chief Administrator, PUDA for a speaking decision.
    • The Chief Administrator subsequently rejected her claim for waiver of interest on instalments but extended the moratorium period for construction, noting that development works in the commercial pocket had been completed on 16 June 2017.
    • Gupta thereafter approached the Real Estate Regulatory Authority, Punjab seeking three reliefs: refund of interest charged on instalments, extension of the non-construction period, and interest under Section 18 of RERA.
    • The Authority dismissed her complaints. On appeal, however, she restricted her claim only to interest for delayed possession under Section 18.

    RERA Appellate Tribunal Awards Interest for Delayed Possession

    • The Real Estate Appellate Tribunal, Punjab allowed Gupta’s appeals on 12 May 2022.
    • For SCO Site No. 1, it awarded interest for delayed possession from 1 March 2016 to 19 October 2017.
    • For SCO Site No. 2, it awarded interest from 4 August 2017 to 19 October 2017 on the amount deposited up to that date, applying Rule 16 of the Punjab State Real Estate (Regulation and Development) Rules, 2017.
    • Bathinda Development Authority challenged those orders before the Punjab and Haryana High Court.

    Development Authority Questions Maintainability of RERA Proceedings

    • The Authority argued that the dispute arose from allotments governed by the Punjab Regional and Town Planning and Development Act, 1995 (PRTPD Act).
    • According to it, after the Chief Administrator passed the order dated 27 May 2019 in exercise of appellate powers under Section 45 of the PRTPD Act, Gupta’s appropriate remedy was to file a revision before the State Government under Section 45(8) rather than initiating proceedings under RERA.
    • The High Court rejected this contention.
    • It noted that Gupta had relinquished her other claims and restricted the dispute before the RERA authorities to the statutory remedy of interest under Section 18 of RERA. Her claim was therefore independently founded on the RERA Act.
    • The Court also noted that the maintainability objection had not been raised by the Development Authority before either the RERA Authority or the Appellate Tribunal and was being advanced for the first time at a belated stage.

    Section 18 RERA Creates Statutory Right to Interest for Delay

    • The High Court examined Section 18 of the RERA Act, which provides remedies where a promoter fails to complete or give possession of an apartment, plot or building according to the agreed terms.
    • Where the allottee does not wish to withdraw from the project, the proviso to Section 18(1) requires the promoter to pay interest for every month of delay until possession is handed over, at the prescribed rate.
    • The issue therefore turned on whether Bathinda Development Authority was a β€œpromoter” and whether there had actually been delay in making the sites ready for possession.

    Development Authority Expressly Covered by Definition of β€˜Promoter’

    • The High Court referred to Section 2(zk)(iii) of the RERA Act, which expressly includes a development authority or other public body within the definition of β€œpromoter” in relation to specified buildings, apartments and plots.
    • The Court therefore held that there was β€œno doubt” that Bathinda Development Authority was covered within the statutory definition of promoter.
    • This finding is important because it confirms that a public development authority cannot seek exemption from RERA’s promoter obligations merely because it is a statutory or State authority rather than a private developer.

    β€˜As Is Where Is’ Clause Does Not Excuse Delayed Development

    • Bathinda Development Authority relied heavily on two provisions in the allotment letter.
    • First, the plot had been offered on an β€œas is where is” basis. Second, the allotment letter stated that possession would be given within 90 days and, if the allottee did not take possession within that period, possession would be deemed to have been handed over on the due date.
    • The High Court was not persuaded.
    • It reasoned that if the β€œas is where is” clause completely absolved the Authority from carrying out development, there would have been no reason for the Authority itself to spend resources and time undertaking development work.
    • The record showed that development of the site was, in fact, the Authority’s responsibility.

    The Court importantly observed that:

    • β€œMere physical possession without any basic amenities would serve no purpose”
    • because construction and commercial activity could not practically be carried out without the necessary basic infrastructure.

    Electricity Is a Basic Amenity; Site Was Ready Only on 19 October 2017

    The date on which the sites could genuinely be treated as ready for possession became a central issue.

    An RTI response showed that:

    • civil and public health works were completed on 16 June 2017;
    • electrical works were completed on 28 April 2017;
    • transformers were installed on 1 March 2017; and
    • electricity supply became available only on 19 October 2017.
    • The Chief Administrator had treated 16 June 2017 as the completion date, apparently without treating actual electricity supply as essential.
    • The High Court disagreed.
    • It held that electricity was a basic amenity necessary for construction activity, particularly because machinery used at a construction site requires power. It therefore affirmed the Appellate Tribunal’s conclusion that the sites were actually ready for possession only on 19 October 2017.

    Extension of Construction Moratorium Was an Indirect Admission of Delay

    • The Court also identified what it considered an inconsistency in the Authority’s stand.
    • The Chief Administrator had extended the three-year moratorium period for construction on the ground that the commercial pocket became ready only after development work was completed.
    • According to the High Court, if there had genuinely been no delay on the Authority’s part, there would have been no need to extend the construction moratorium.
    • The extension was therefore treated as an indirect admission through the Authority’s own conduct that delay had occurred.

    Allottee Cannot Face Penalty for Delay While Promoter Faces No Consequence

    • The High Court also addressed the imbalance that would arise if the Authority’s interpretation were accepted.
    • It observed that an allottee could be required to pay penalty charges for failing to complete construction within the stipulated period. It would therefore be anomalous if there were no corresponding consequences for the promoter’s delay in providing possession, especially when Section 18 of RERA expressly provides a statutory remedy for such delay.

    Supreme Court’s Arifur Rahman Khan v. DLF Southern Homes Applied

    The High Court relied on the Supreme Court’s judgment in:

    Wg. Cdr. Arifur Rahman Khan and Aleya Sultana v. DLF Southern Homes Pvt. Ltd., (2020) 16 SCC 512.

    • The Court referred to the Supreme Court’s recognition that agreements between developers and purchasers often do not operate on an equal footing: stringent obligations imposed on purchasers are frequently not mirrored by equivalent obligations on developers to meet timelines.
    • Bathinda Development Authority argued that Gupta had participated in the auction with her β€œeyes wide open.”
    • The High Court rejected this reasoning, observing that participation in an open auction could not mean that the allottee should have anticipated that the Authority itself would delay development work.
    • The fact that the site had been allotted through an auction did not confer any right upon the Authority to delay development. Once delay occurred, the statutory consequences under RERA had to follow.

    State Development Authority Cannot Claim Preferential Treatment Over Private Promoter

    • The High Court made another significant observation concerning public development authorities.
    • It held that no concession could be claimed by a State Development Authority merely because it was a public body rather than a private promoter.
    • Indeed, the Court observed that the obligation upon the State was greater because it was itself a law-enforcement agency, particularly where it had maximised revenue by disposing of property through an open auction.
    • The ruling therefore places public development authorities squarely within the accountability framework established by RERA where the statutory definition of promoter is attracted.

    Earlier PUDA Order Did Not Bar Section 18 Claim

    • The Authority further argued that the Chief Administrator’s order dated 27 May 2019 had never been challenged and continued to remain in force.
    • The High Court rejected this objection because the earlier proceeding concerned a different relief.
    • The Chief Administrator had rejected Gupta’s request that interest should not be charged on her instalments during the development period.
    • The RERA proceedings, by contrast, concerned her affirmative statutory entitlement to receive interest from the promoter for delayed possession under Section 18.
    • The two issues were therefore legally distinct.

    Other Allottees Taking Possession Earlier Does Not Defeat Statutory Right

    • The Authority also claimed that similarly situated allottees had taken possession earlier.
    • The High Court noted that no material had been placed on record to substantiate this assertion. More importantly, even assuming it to be factually correct, the conduct of other allottees could not extinguish Gupta’s rights arising from the statutory provisions.

    Final Decision: Bathinda Development Authority’s Appeals Dismissed

    • The Punjab and Haryana High Court found no reason to interfere with the Real Estate Appellate Tribunal’s order.
    • Both RERA Appeal No. 6 of 2023 and RERA Appeal No. 12 of 2023 filed by Bathinda Development Authority were dismissed.

    Consequently, Leela Gupta succeeded, and the Appellate Tribunal’s award of delayed-possession interest remained intact:

    SCO SitePeriod for Which Interest Was Awarded
    SCO Site No. 11 March 2016 to 19 October 2017
    SCO Site No. 24 August 2017 to 19 October 2017
    • The interest was to operate on the deposited amount in accordance with the applicable RERA framework and Rule 16 of the Punjab State Real Estate (Regulation and Development) Rules, 2017.

    Key Takeaway

    The judgment establishes three important RERA principles. A Development Authority is expressly covered within the definition of β€œpromoter” under Section 2(zk); an β€œas is where is” or deemed-possession clause cannot automatically defeat the statutory entitlement under Section 18 where the site was not practically ready for possession; and essential infrastructure such as actual electricity supply may be relevant in determining when a commercial site became genuinely ready for possession.

    Most importantly, the High Court made clear that State development authorities cannot claim a more favourable standard than private promoters when RERA obligations apply.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Supreme Court: Contractual Bar on Interest Cannot Be Invoked Belatedly After Consenting to Arbitration

    Supreme Court: Contractual Bar on Interest Cannot Be Invoked Belatedly After Consenting to Arbitration

    Date: 26.09.2026

    The Supreme Court has held that a party cannot ordinarily raise a contractual or legal plea at a later stage of arbitration proceedings when it had the opportunity to raise the plea before the Arbitral Tribunal but failed to do so. Such conduct can amount to waiver or abandonment of the plea, particularly where allowing it later would prejudice the opposite party.

    In Union of India v. M/s Susaka Pvt. Ltd. & Ors., the Supreme Court dismissed the Union of India/Railways’ appeal challenging an arbitral award of interest, holding that the Railways could not rely for the first time before the Supreme Court upon a contractual clause prohibiting interest when it had failed to properly raise and pursue that objection before the Arbitral Tribunal and the courts below.

    Dispute Arose From Railway Works Contract

    • The dispute arose from a works contract awarded by the Union of India (Railways) to M/s Susaka Pvt. Ltd. on 19 December 1994 for repair work relating to 25 stators of TAO-659 Traction Motors of Electric Locomotives, Type WCAMI, at Electric Loco Shed, Valsad.
    • Disputes subsequently arose during execution of the contract. Since Clause 56(1) of the General Conditions of Contract (GCC) contained an arbitration mechanism, Susaka invoked arbitration and approached the Bombay High Court under Section 11(5) of the Arbitration and Conciliation Act, 1996 for constitution of an Arbitral Tribunal.
    • By an order dated 27 July 2001, the High Court, with the consent of the parties, referred the claims to a three-member Arbitral Tribunal consisting of Railway officials. Significantly, the reference expressly stated that the arbitrators would also be free to decide pre-reference interest, pendente lite interest, further interest and costs, considering the agreement.

    Arbitral Tribunal Awards β‚Ή27.62 Lakh

    • The Arbitral Tribunal delivered a unanimous reasoned award dated 11 September 2002, partly allowing Susaka’s claims.
    • The award covered, among other things, loss due to under-utilisation of equipment, material purchased but not utilised, loss of profit, overheads, payment under the price-variation clause and interest.
    • The table reproduced on pages 5 and 6 of the Supreme Court judgment records a total award of β‚Ή27,62,214, including β‚Ή12,89,033 towards interest.
    • The central issue that eventually reached the Supreme Court concerned the Tribunal’s power to award interest for different periods. The award provided for pre-reference interest at 15% per annum, pendente lite interest at 12% per annum and post-award interest at 18% per annum.

    Railways Challenges Award Under Section 34

    • Aggrieved by the award, the Union of India filed proceedings under Section 34 of the Arbitration and Conciliation Act, 1996 before a Single Judge of the Bombay High Court.
    • The Single Judge partly interfered with the award by modifying the date from which interest would be payable in relation to two claims. However, the Railways’ objections concerning the remaining claims were rejected and the award was otherwise upheld.
    • Susaka challenged the limited interference before the Division Bench. The Railways, however, did not file an appeal against the part of the Single Judge’s order rejecting its other objections. Consequently, that part of the award attained finality.
    • The Division Bench subsequently allowed Susaka’s appeal, holding that no ground under Section 34 had been established for modifying the award in relation to interest. This effectively restored the arbitral award in its entirety.
    • The Union of India then approached the Supreme Court.

    Railways Relies on Clause 13(3) to Challenge Interest

    • Before the Supreme Court, the Railways relied heavily upon Clause 13(3) of the GCC.
    • According to the Railways, Clause 13(3) stipulated that no interest would be payable on earnest money, security deposit or amounts payable to the contractor under the contract, except Government securities.
    • It therefore argued that the Arbitral Tribunal had acted contrary to the contract in awarding interest and that the award was liable to be set aside under Section 34.
    • Susaka opposed the argument on a fundamental procedural ground: the Railways had not raised and pursued the Clause 13(3) objection before the Arbitral Tribunal or the courts below and therefore could not introduce it for the first time before the Supreme Court under Article 136 of the Constitution.

    Supreme Court: Railways Had Consented to Arbitration of Interest Claim

    • The Supreme Court accepted Susaka’s objection.
    • The Court found that the Railways had not raised the plea based on Clause 13(3) in its reply before the Arbitral Tribunal. More importantly, during the Section 11(5) proceedings, the Railways had expressly consented to referring the question of interest to arbitration.
    • The Court observed that if the Railways intended to rely on Clause 13(3), it could have raised the objection when the dispute was referred to arbitration or expressly reserved its right to raise the objection before the Tribunal.
    • It did neither.
    • The Railways thereafter participated in the arbitration and allowed the Tribunal to adjudicate the interest issue on merits without specifically pleading Clause 13(3).

    Raising a Ground in Section 34 Petition Is Not Enough If It Is Not Pressed

    • The Supreme Court also noticed an important procedural aspect.
    • Although the Railways included the Clause 13(3) objection as a ground in its Section 34 proceedings before the Single Judge, the ground was not pressed during arguments. It was also not subsequently raised before the Division Bench.

    The Supreme Court therefore described the case as one of:

    β€œwaiver or/and abandonment of a plea at the initial stage itself.”

    Pleas Must Be Raised at the Appropriate Stage

    • The judgment lays down an important litigation and arbitration principle: where a pleaβ€”whether based on fact or lawβ€”is available to a party, it must be raised at the appropriate stage in accordance with law.
    • If a party fails to raise the plea, or gives it up by consent, it may subsequently be precluded from resurrecting it on the principle of waiver, particularly where doing so would prejudice the opposite party.
    • The Court referred to the maxim β€œCuilibet licet renuntiare juri pro se introducto”, explaining that a person may waive the advantage of a law made solely for his or her individual benefit and protection, provided no public right or public policy is infringed. Susaka Pvt. Ltd. & Ors.

    Failure to Appeal Against Rejection of Other Claims Also Proved Fatal

    • There was another reason why the Railways’ challenge failed.
    • The Single Judge had substantially rejected the Railways’ Section 34 challenge except in relation to two interest claims. Yet the Railways did not appeal against the portion of the order rejecting its objections.
    • The Supreme Court held that this part of the Single Judge’s decision had therefore attained finality.
    • Had the Railways wished to keep those issues alive, it was required to challenge that portion before the Division Bench. Only thereafter could an adverse determination potentially have been pursued before the Supreme Court under Article 136.

    Arbitral Tribunal Has Power to Award Interest

    • The Supreme Court also made important observations concerning an arbitrator’s power to award interest.
    • It held that an award of interest on arbitrable claims is not inherently illegal, contrary to public policy, per se bad in law or beyond the powers of an Arbitral Tribunal.
    • The Court specifically referred to Section 31(7)(a) and (b) of the Arbitration and Conciliation Act, 1996, observing that these provisions empower an Arbitral Tribunal to award interest on the awarded sum, although that power remains subject to the agreement between the parties.
    • This qualification is important: the Supreme Court did not hold that an arbitrator can disregard an express contractual prohibition on interest. Rather, the decision turned substantially on the Railways’ failure to timely raise and preserve its contractual objection.

    Courts Should Not Lightly Interfere With Arbitral Awards

    • The Supreme Court further reiterated the limited nature of judicial interference with arbitral awards.
    • Once parties have chosen their arbitrators and authorised them to adjudicate specified disputes, their decision should ordinarily be respected. Courts should interfere only where the award falls within one of the grounds prescribed under Section 34 of the Arbitration and Conciliation Act, 1996.
    • This part of the judgment reinforces the principle that Section 34 proceedings are not intended to provide parties with an unrestricted opportunity to reargue matters already submitted to arbitration.

    Supreme Court Refers to Firm Kaluram Sitaram v. Dominion of India

    The judgment expressly refers to the Bombay High Court decision in:

    Firm Kaluram Sitaram v. The Dominion of India, AIR 1954 Bombay 50.

    • The Supreme Court recalled former Chief Justice M.C. Chagla’s observations concerning the State’s reliance on technical defences against citizens.
    • Applying that principle, the Supreme Court criticised the Railways for pursuing a technical legal argument up to the Supreme Court even though the plea had not been properly raised at the relevant stages of the proceedings.

    Final Decision: Union of India’s Appeal Dismissed

    • The Supreme Court ultimately found no merit in the Union of India’s appeal and dismissed it.
    • Accordingly, M/s Susaka Pvt. Ltd. succeeded before the Supreme Court, and the Railways’ attempt to challenge the award of interest by relying upon Clause 13(3) of the GCC failed.
    • The judgment is particularly significant for arbitration proceedings because it demonstrates that a potentially available contractual defence can be lost if it is not specifically pleaded, pressed and preserved at the appropriate stage.
    • It also makes an important distinction between the substantive contractual limitation on an arbitrator’s power to award interest and the procedural question of whether a party has preserved its right to invoke that limitation.

    Key Takeaway

    A party cannot participate in arbitration without raising an available contractual objection, allow the Tribunal to decide the issue on merits, fail to press the objection in Section 34 proceedings, and then seek to revive it for the first time before the Supreme Court.

    The decision in Susaka therefore stands as an important authority on waiver and abandonment of pleas in arbitration proceedings, while also recognising that Section 31(7) empowers arbitrators to award interest subject to the parties’ agreement.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download:

  • Bombay High Court: Railway Board Circular Cannot Override 2013 Land Acquisition Act

    Bombay High Court: Railway Board Circular Cannot Override 2013 Land Acquisition Act

    Date: 26.09.2026

    The Bombay High Court has held that tenants whose structures are acquired for a public project fall within the definition of β€œaffected family” under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and are entitled to statutory rehabilitation and resettlement benefits.

    The Division Bench rejected an attempt by the Dedicated Freight Corridor Corporation of India Limited (DFCCIL) to rely upon a Railway Board-approved Entitlement Matrix to restrict the tenants’ entitlement to merely three months’ notice and β‚Ή10,000 as shifting allowance.

    The Court categorically held that administrative instructions issued by the Ministry of Railways cannot override the statutory provisions of the 2013 Land Acquisition Act. It directed payment of β‚Ή14.17 lakh to each petitioner, together with statutory interest under Section 80β€”9% per annum for the first year from taking possession and 15% per annum from the second year onwards.

    Dispute Arose From Dedicated Freight Corridor Project in Raigad

    • The petitioners were tenants occupying structures acquired by DFCCIL for the Dedicated Freight Corridor passing through Alibag, District Raigad.
    • Their grievance was that although competent authorities had already confirmed their eligibility and quantified the monetary compensation payable to them, DFCCIL subsequently prevented the amounts from being disbursed.
    • The petitioners had approached the Appellate Authority for Rehabilitation in 2021 as members of affected families/project-affected persons. Possession of their structures was admittedly taken during 2021–2022.

    Appellate Authority Had Already Declared Tenants Eligible for Compensation

    • On 16 June 2022, the Deputy Commissioner (Rehabilitation), Konkan Division, acting as the Appellate Authority, allowed the petitioners’ appeals and held that they were eligible to receive compensation.
    • Those orders referred to the Maharashtra Government Resolution dated 22 May 2018, which provided the mechanism for payment of compensation to affected persons.
    • DFCCIL filed review applications challenging the petitioners’ eligibility, but the review applications were rejected. Consequently, the orders confirming their eligibility remained undisturbed.

    β‚Ή14.17 Lakh Compensation Determined for Each Petitioner

    • Following the determination of eligibility, the District Rehabilitation Officer submitted a proposal to the State Government seeking approval for payment.
    • Eventually, on 6 November 2025, the Deputy Collector (Rehabilitation), acting as Administrator for Rehabilitation for the project, passed a reasoned order determining compensation of:

    β‚Ή14,17,000 for each petitioner

    • DFCCIL and the rehabilitation authority thereafter informed the concerned bank regarding payment. In fact, instructions were issued on 6 November 2025 for transferring a substantial portionβ€”β‚Ή10 lakh to each petitioner through RTGS.
    • The dispute took a different turn shortly thereafter.

    DFCCIL Suddenly Halts Compensation

    • On 24 November 2025, the Project Manager of DFCCIL wrote to the District Rehabilitation Officer taking a position contrary to the steps already undertaken for payment.

    DFCCIL asserted that because the petitioners were merely tenants, they were entitled only to:

    • three months’ written notice; and
    • β‚Ή10,000 towards shifting allowance.

    For this position, DFCCIL relied upon an Entitlement Matrix based on its September 2012 Relief and Rehabilitation Plan.

    The District Rehabilitation Officer responded on 8 December 2025, pointing out that the State Government had already approved the petitioners’ eligibility and their entitlement to the compensation.

    Despite this, DFCCIL did not release the amounts. The petitioners issued a legal notice on 5 March 2026 and thereafter approached the Bombay High Court in April 2026.

    DFCCIL Relies on Railway Board’s 2015 Entitlement Matrix

    • Before the High Court, DFCCIL relied principally on a letter dated 23 May 2015 issued by the Director Planning (Special), Ministry of Railways, Railway Board, to the Managing Director of DFCCIL.
    • The communication approved an Entitlement Matrix for Dedicated Freight Corridor projects based on DFCCIL’s September 2012 Rehabilitation and Resettlement Plan.
    • DFCCIL argued that the Matrix governed compensation payable to lessees and tenants.
    • It also contended that compensation had already been paid to the owners of the structures occupied by the petitioners and, therefore, the tenants could not separately claim the β‚Ή14.17 lakh quantified by the rehabilitation authority.
    • Another argument was based on the Maharashtra Government Resolution dated 22 May 2018. DFCCIL claimed that since the structures stood on Gaothan land, the second schedule to the Government Resolution applied and only owners were entitled to compensation.

    Tenants Expressly Included in Definition of β€˜Affected Family’

    • The High Court examined Section 3(c) of the 2013 Act, particularly Section 3(c)(ii).
    • The provision includes within β€œaffected family” a family that does not own land but whose member or members may be:
    • β€œagricultural labourers, tenants including any form of tenancy…”
    • subject to the statutory requirements concerning the impact of acquisition on livelihood.
    • The Court found that it was undisputed that the petitioners were tenants in the structures acquired by DFCCIL.
    • It consequently held that the petitioners were covered by the statutory definition and were entitled to compensation under the 2013 Act by applying Schedule II.

    Section 31 Requires Rehabilitation and Resettlement Award for Affected Families

    • The Division Bench also examined Section 31 of the 2013 Act, which requires the Collector to pass a Rehabilitation and Resettlement Award for each affected family in accordance with the entitlements under the Second Schedule.
    • Such an award may contain rehabilitation and resettlement amounts, bank account details, house sites, land allotments, subsistence and transportation allowances, amounts for cattle sheds and petty shops, benefits for artisans and small traders, employment-related entitlements, annuity and other statutory benefits.
    • Reading Section 31 together with Section 3(c) and Schedule II, the Court concluded that the petitioners’ status as tenants did not exclude them from the statutory rehabilitation framework.

    Railway Board’s Administrative Instructions Cannot Override Statute

    • The most significant legal finding concerns the relationship between the Railway Board’s administrative instructions and the 2013 Act.
    • The High Court rejected DFCCIL’s reliance on the Railway Board letter dated 23 May 2015 and the corresponding Entitlement Matrix.

    The Bench held:

    • β€œSuch instructions cannot prevail upon the statutory provisions”
    • and found that the Railway Board communication could not override the statutory provisions of the 2013 Act.
    • Thus, an administrative compensation policy or departmental entitlement matrix cannot be invoked to reduce or take away a benefit that the governing legislation confers upon an eligible affected family.

    DFCCIL’s Objection Was Raised at a Belated Stage

    • The High Court also found DFCCIL’s conduct significant.
    • The petitioners’ eligibility had already been determined by the Appellate Authority in June 2022. DFCCIL’s review applications had failed. The competent authority subsequently quantified compensation at β‚Ή14.17 lakh each.
    • More importantly, the Chief General Manager of DFCCIL had itself joined the competent authority in directing the bank to transfer β‚Ή10 lakh to each petitioner.
    • Only thereafter did the Project Manager issue the communication dated 24 November 2025 objecting to payment and invoking the 2015 Entitlement Matrix.
    • The Court characterised this objection as belated.

    Government Resolution Also Could Not Reduce Statutory Benefits

    • DFCCIL’s reliance on the Maharashtra Government Resolution dated 22 May 2018 also failed.
    • The High Court noted that paragraph 6 of the Government Resolution itself recognised that where the compensation or relief available under the 2013 Act was higher, the higher statutory benefit would prevail.
    • The Bench connected this principle with Section 108 of the 2013 Act, which gives affected families the option to avail themselves of better compensation and rehabilitation and resettlement benefits.
    • Consequently, DFCCIL could not rely upon the second schedule to the Government Resolution to reduce the petitioners’ statutory entitlement.

    Bombay HC Orders β‚Ή14.17 Lakh Compensation to Each Tenant

    • The Court rejected the grounds advanced by DFCCIL and allowed all the connected writ petitions.
    • It held that each petitioner was entitled to:
    • β‚Ή14,17,000 as compensation, along with statutory interest
    • The principal amount had already been deposited by DFCCIL. The Court therefore ordered that β‚Ή14.17 lakh be disbursed to each petitioner within two weeks.

    9% Interest for First Year and 15% Thereafter

    • The petitioners had sought interest at 18% per annum.
    • The High Court did not grant the claimed 18% rate. Instead, it applied the statutory interest mechanism contained in Section 80 of the 2013 Act.
    • According to the judgment, delayed payment attracts:
    • 9% per annum for the first year from the date possession was taken, and 15% per annum from the second year onwards.
    • The Court considered statutory interest appropriate because DFCCIL had taken an β€œunreasonable stand belatedly” and had deprived the petitioners of their rightful dues without justification.
    • It particularly noted that DFCCIL had initially directed substantial payment of β‚Ή10 lakh each through RTGS and then suddenly reversed its position and objected to the disbursement.

    Time-Bound Directions for Payment of Interest

    • The High Court laid down a specific schedule for implementation.
    • The competent authority was directed to calculate the interest payable to each petitioner within four weeks.
    • It must thereafter communicate the calculation to the Chief General Manager and Project Manager of DFCCIL within one week.
    • DFCCIL must then deposit the interest amount with the competent authority within two weeks, following which the authority must disburse it to the petitioners within one further week.

    Final Decision

    • The Bombay High Court made the rule absolute and allowed all seven connected writ petitions.

    The petitioners were:

    • Sanjay Baban Girhe, Heena Suhas Niromkar, Vijaykumar Subedar Mourya, Rajendra Muktaji Shinde, Vandana Ulhas Girhe, Mahesh Mahillappa Kallure and Sambhaji Shivhar Mule.
    • Each petitioner is to receive β‚Ή14.17 lakh plus statutory interest under Section 80 of the 2013 Act.

    Key Takeaway

    The judgment establishes an important principle for land acquisition and infrastructure projects: tenancy does not by itself exclude a person from rehabilitation and resettlement benefits under the 2013 Land Acquisition Act.

    Where a tenant satisfies the statutory definition of an β€œaffected family” under Section 3(c), the entitlement must be determined under the Act, including Section 31 and Schedule II. An internal policy, project-specific Entitlement Matrix, Railway Board instruction or State Government resolution cannot be used to dilute a superior statutory entitlement.

    The ruling is particularly significant for infrastructure projects undertaken by government corporations because the Court made clear that administrative instructions must yield to the governing legislation, while Section 108 protects an affected family’s entitlement to opt for better compensation and rehabilitation benefits.

    Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

    Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

    Handy Download: