Delhi HC Holds Service-Deficiency Claims Are for Arbitrator to Decide

Date: 18.11.2026

The Delhi High Court has allowed an application for appointment of a sole arbitrator in a dispute arising from a government security-surveillance and manpower-services contract, while requiring the parties to first attempt settlement through court-annexed mediation.

Background of the dispute

The dispute arose from a service contract awarded through the Government e-Marketplace (GeM) platform. The successful service provider entered into Contract No. GEMC-511687716681565 on 6 October 2020 with a government education authority for security surveillance and manpower services.

The contract contained a two-part dispute-resolution framework:

  • The General Terms and Conditions incorporated the GeM dispute-resolution mechanism.
  • The Special Terms and Conditions expressly provided for arbitration of questions, disputes, or differences arising under the contract.

Under the arbitration provision, the arbitral award would be final and binding, and proceedings would be governed by the Arbitration and Conciliation Act, 1996, as amended.

Invocation of arbitration

Following disputes concerning the contractual arrangement, the service provider invoked arbitration through a legal notice dated 26 April 2025. It subsequently approached the Delhi High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator.

The respondent authority did not contest the existence of the arbitration agreement. It nevertheless asserted that there had been deficiencies in the contracted services and indicated that it may pursue counterclaims.

Court’s approach: merits belong before the arbitral tribunal

The Court held that allegations relating to deficient performance and possible counterclaims are matters for determination by the arbitral tribunal, rather than issues that prevent appointment at the Section 11 stage.

This reflects the limited scope of judicial intervention while appointing an arbitrator. Where a valid arbitration clause is undisputed, substantive disputes, preliminary objections, claims, counterclaims, and questions of arbitrability are ordinarily left for adjudication in arbitration.

Accordingly, the Court allowed the petition and appointed an independent sole arbitrator to determine the dispute.

Mediation before commencement of arbitration

The parties agreed that mediation should be attempted first. With their consent, the Court referred the matter to the Delhi High Court Mediation and Conciliation Centre.

The parties were directed to appear before the mediation centre on 12 January 2026 at 4:30 PM. If the dispute is not resolved through mediation, the sole arbitrator will enter upon the reference after eight weeks from that date.

The direction balances consensual dispute resolution with the parties’ contractual right to arbitration. It provides an opportunity for settlement without delaying the ultimate adjudication of unresolved claims.

Arbitration under DIAC rules

The Court directed that the arbitration be conducted under the aegis and rules of the Delhi International Arbitration Centre (DIAC). The arbitrator’s fees and administrative costs will be regulated by the DIAC (Administrative Cost and Arbitrators’ Fees) Rules, 2018.

Before commencing the reference, the appointed sole arbitrator must make the disclosure required under Section 12 of the Arbitration and Conciliation Act, 1996. This statutory requirement is designed to ensure transparency regarding circumstances that may give rise to justifiable doubts about the arbitrator’s independence or impartiality.

Rights and objections remain open

The order expressly preserves all rights and contentions of both parties. The arbitral tribunal may therefore consider:

  • Whether particular claims are arbitrable;
  • Any preliminary jurisdictional or procedural objections;
  • The service provider’s claims;
  • The government authority’s counterclaims; and
  • The merits of each party’s case.

The Court did not decide these issues. Its ruling was confined to facilitating the agreed dispute-resolution mechanism by appointing a sole arbitrator.

Key legal takeaway

The decision demonstrates that, when an arbitration agreement is admitted, disputes over contractual performance do not usually derail the appointment of an arbitrator. Such matters are for the arbitral tribunal to examine on evidence. It also shows the Court’s preference for mediation as an initial settlement mechanism, followed by institutional arbitration where settlement is unsuccessful.

The parties now have a defined framework for resolving the contractual dispute through mediation and, if required, DIAC-administered arbitration under the Arbitration and Conciliation Act, 1996.

Aadrikaa Legal Services is a trusted legal and regulatory support partner providing end-to-end legal solutions to law firms, corporate organizations, and businesses across India. We specialize in paralegal services, litigation support, tax and regulatory matters, delivering reliable, efficient, and result-oriented legal assistance.

Our services include comprehensive paralegal support, drafting and documentation, legal research, case management, litigation handling, and representation support across various judicial and quasi-judicial forums. We also assist in direct and indirect tax matters, customs, GST, corporate regulatory compliance, and legal advisory.

Handy Download:

Comments

Leave a Reply

Discover more from π€πšππ«π’π€πšπš π‹πžπ πšπ₯ π’πžπ«π―π’πœπžπ¬ (𝐀𝐋𝐒)

Subscribe now to keep reading and get access to the full archive.

Continue reading